Knowledge quiz

It's time to put what you've learned to the test, get 5 right to pass this unit.

1.

Which of the following statements are true about PPM?

There are three correct answers.
2.

A portfolio bucket can contain lower-level portfolio buckets and portfolio items at the same time.

Choose the correct answer.
3.

What must you do to achieve a standardized evaluation of the costs, revenue, budgets, or commitments of your portfolio items?

Choose the correct answer.
4.

By default, you cannot link Microsoft Project, Project System, and Project Management with PPM.

Choose the correct answer.
5.

When you upload project data to PPM or Project Management, you have to manually create the corresponding work breakdown structure elements and roles.

Choose the correct answer.
6.

NEW, RENEW, and ENABLE are the three components of the SAP user strategy.

Choose the correct answer.

Log in to track your progress & complete quizzes