Outlining Production Planning in SAP S/4HANA
Explaining and Reviewing Master Data and the Alert Monitor
Understanding Planning Strategies in SAP S/4HANA PP/DS
Executing Production Planning in SAP S/4HANA PP/DS
Understanding Detailed Scheduling in SAP S/4HANA PP/DS
Understanding Optimization in SAP S/4HANA PP/DS
Understanding the Interaction of Planning in SAP S/4HANA and SAP S/4HANA PP/DS

Knowledge quiz

It's time to put what you've learned to the test, get 6 right to pass this unit.

1.

When Advanced Planning is used, a planned order should always be converted to a production order in Advanced Planning.

Choose the correct answer.
2.

When is the planning file updated?

Choose the correct answer.
3.

Setup times can be entered directly in the PPM/PDS or they can be stored in a setup matrix according to the setup status.

Choose the correct answer.
4.

What do you determine with the product heuristic?

Choose the correct answer.
5.

Which lot-size procedure would you use if you always receive full pallets?

Choose the correct answer.
6.

How can you simulate data in PP/DS?

There are two correct answers.
7.

Assume you have a planning time fence in place in PP/DS and a new sales order comes in with a requirement date within this planning time fence. What would be the consequence when the MRP run is started?

Choose the correct answer.