
The figure, Key Objectives for Production Planner, shows you the challenges with which the production planner has to deal.
In summary, production planners, while focused around releasing the plan for production in the immediate horizons, also need to keep their eyes open in a proactive manner to address potential issues before they become critical.

The production source header is modeled similarly to the production version in SAP ERP or SAP S/4HANA. The naming standard could be Plant_Product_Version.
- 4-letter version can be used as mmnn (mm = 00, 01 etc. to represent production line or resource; similarly nn can represent BOM versions).
- Naming standards enable better troubleshooting later.
Typically, production facilities have multiple resources to produce the same product. Whether to model them collectively as single resource or not depends on factors such as:
- Consumption rate, for example, fast vs. slow
- Technical capability - can handle only certain sizes or packages or ingredients
- Production costs
Priority is determined by production cost - this allows you to switch from the main production line to an alternate production line by modeling one production source header for each line. Relative production costs across multiple plants also enable sourcing of demands to alternate sites or to an external contract manufacturer.
In the case of a contract manufacturer, the vendor must be modeled as location type P (Plant) in SAP Integrated Business Planning to model capacity constraints.

There are many key figures in supply planning - most are common to time-series-based heuristics and the optimizer. However, the optimizer uses cost key figures. Additionally, the max key figures are respected by the optimizer and finite heuristic only.
Frozen horizon allows you to model the hand-off between planning and execution - for more information, see the next figure.
Additional Parameters in Production Source Header
- Min and Incremental Lot Size - enabled for horizons specified globally in the optimizer profile.
- Production Lead Time - controls when capacity or components are consumed, if not on finish date - in the production source header. For more information, see the help documentation for SAP Integrated Business Planning.

Since SAP IBP 2111 key figure Confirmed Production can be used to support firm production inputs from SAP ERP instead of Adjusted Production.
The following are the two types of planner adjustments:
- Fixed: This is made possible by the Adjusted Production Interactive key figure.
- Minimum: The planner wants the minimum quantity to be planned even if there is no demand in that period. Additional quantity may be planned on top, if the demand exceeds the minimum specified.
Both types of adjustments are specific to the periods they are entered - if there is not enough capacity or other constraints make it impossible to achieve the specified values, the system does NOT shift unmet quantity to other time buckets. Do not use these key figures in lieu of anticipated demands.
Also, minimum and incremental values are ignored when adjusted production is used. If there is inadequate capacity, the engine will plan for as much as possible, once again disregarding rounding values.
Using a Max Production of 0 will ensure that there is no production for that product in that period.

Available Capacity acts as a hard constraint for production. It is not possible to model changeover and sequence dependent changeover costs - hence model average capacity as available capacity.
Min Capacity Utilization can be used to achieve capacity leveling. It could also result in push production; for example, boilers, furnaces, and reactors cannot be brought down easily without wasted time and additional costs. Min Capacity usage violation cost rates allows for violation if justified by other costs.
Capacity Expansion may be modeled for extra shift. This incurs additional costs. There are no step increments; that is, no minimum or incremental steps (not supported due to high optimizer performance degradation).
- More commonly modeled to ensure that the adjusted production quantity is met by the optimizer, regardless of the line capacity.
- Set Capacity Supply Expansion Cost Rate as higher than Non-Delivery Cost Rates - resulting in use of capacity expansion for only adjusted production (which carry very high internal costs) and not for customer demands or target inventory.

The figure shows additional modeling parameters and inputs.






























