OM enables you to depict your company in the past, present, and future using the following information:
- Validity periods
- Plan versions
- Plan statuses
The figure Planning in OM shows the existing organizational structure of an enterprise on the left. Using OM, you can plan any type of enterprise restructuring or reorganization and then reproduce the structure in the system. This enables you to prepare for future staff requisitions or changes and respond to the situation accordingly.
Methodology: Plan Versions
Plan versions allow you to depict and manage several organizational plans in the system at the same time. You can use plan versions to simulate and compare various scenarios. However, only one plan version can be integrated. This plan version represents the valid organizational plan, and is flagged as the active or integrated plan version.
You must define the active plan version when you integrate the SAP system.
As a rule, you cannot change the active plan version at a later date. If integration is active, the plan version you select here as active is the integrated plan version, regardless of the system. In the parameter group PLOGI PLOGI, enter the plan version that is to be the active plan version in the Semantic Abbreviation Value field. Once you designate a plan version such as 01 as the active plan version, as a rule it should always be 01. You can update it directly in production or make copies of it to complete various plan scenarios. For example you might copy 01 to 10, 11 and 12. The best case scenario is represented by 10, 11 represents the worst case, and 12 represents an average case scenario. Once the new version is selected, it is copied back into plan version 01 with an effective date. Plan version 01 should always be the active plan version once it is set up that way.
Plan versions exist independently of each other. They can be created as copies of the original plan in statements by using report RHCOPL00 Copy Plan Version. You can change this copy independently of the valid plan. While this option is advantageous, it means that handling plan versions is more complicated.
After the copy is created, both plan versions develop independently of one another. Consequently, the best copy is out-of-date after a matter of hours or days.
Report RHCOPLPT Reconcile Plan Version supports you when transferring data from an inactive plan version to the active and integrated plan version. However, this report is not able to update personal data in infotype 0001. This can lead to inconsistencies in the integration between Personnel Administration (PA) and Personnel Planning (see SAP Note 354019).
The current plan version is the plan version that you are currently working on in the system. You can use the OM_FRAM_PLVAR_DISP switch in the user profile to display the active plan version on the Change Organization and Staffing interface.
Note
Methodology: Plan Status
Infotype records can go through a planning cycle during which they must be accepted or rejected. A plan status is assigned to each infotype record.
An infotype record can be assigned any one of the following statuses:
- Planned status
The planned status indicates that an infotype record (that is operable) is proposed, but not currently active.
- Submitted status
The submitted status indicates that an infotype record has been submitted for review and subsequent approval or rejection by a person or group of persons.
- Approved status
The approved status indicates that an infotype record (that was previously submitted for review) has been accepted or approved.
- Rejected status
The rejected status indicates that an infotype record (that was previously submitted for review) has been rejected.
- Active status
The active status indicates that an infotype record is currently operable.
Objects can be created in either planned or active status.
You must assign a status for every infotype record you create. You do not, however, have to use all the statuses. Many companies only use the active status.
You cannot use plan statuses with all interfaces. Plan statuses are primarily intended for use with the approval procedure in workflow.
The majority of maintenance interfaces can create and maintain only infotype records with the active status.
The report RHAKTI00 allows you to change the status of several objects at the same time.