Project Overview
Planned Costs
Planned Revenues
Budgeting
Materials
Actual Costs
Actual Revenue
Period-End Closing

Using Progress Analysis to Monitor and Evaluate the Project Schedule

Objectives

After completing this lesson, you will be able to:
  • Perform progress analysis
  • Configure progress analysis

Business Example

You have been assigned the task of evaluating period-end processes. As a part of this process, you need to determine the percentage of completion for costs of network activities based on planned, actual, and commitment costs, using progress analysis.

The percentage of completion (POC) describes the ratio of activity performed up to a key date as a percentage of the total work for the activity or project.

Progress Analysis

The following section describes topics related to progress analysis.

Basic Concepts of Progress Analysis

  • Percentage of completion (POC).

    • Specifies the project progress as a percentage.

    • Describes the ratio of activity carried out up to a key date as a percentage of the total work for the activity or project.

    • Is determined on the basis of the chosen measurement method.

  • Earned value.

    • Value of the work done in a project.

    • Describes the costs corresponding with the POC of a project element.

The system distinguishes between the following three values:

  • Values not aggregated: Values display for each object.

  • Aggregated values: Values are aggregated in line with the project hierarchy. You can apply various weighting.

  • CO-PA: The system determines the aggregated POC for the billing element. The aggregation includes project elements that are subordinate to the billing element in the billing structure.

POCs

POCs are recorded under statistical key figures. For reporting purposes, statistical key figures are assigned to value categories.

The term earned value describes costs corresponding to the POC of an activity or project. It is the result of applying the overall planned costs to the POC. Overall planned costs are accumulated planned costs and the budget.

The system uses the planned cost to calculate progress values from the percentage of completion. The budgeted cost of work scheduled is the calculated plan cost based on the percentage of completion. The budgeted cost of work performed is the target costs based on actual percentage of completion. Using these calculations, the system can calculate the schedule variance and cost variance.

Function of Progress Analysis

If you want to effectively control your project, you need to do more than individually studying costs, resources, and schedules. You can draw informed conclusions on the progress and current status of your project only when you compare these values with actual results. Progress analysis enables you to do this. This analysis is suitable for both internal control of a project and external reporting.

You can estimate the POC of WBS elements, activities, and activity elements. You can also calculate POC automatically using existing data. In both cases, a planned POC (expected progress at a specific point in time) and an actual POC (progress actually made at a specific point in time) are determined. By specifying a weighting factor (planned costs, for example), you can aggregate these values in the WBS.

The system uses a factor, such as planned costs, to calculate progress values from POCs:

  • BCWS: budgeted cost of work scheduled (costs according to planned progress)

  • BCWP: budgeted cost of work performed (target costs according to actual progress)

  • Actual costs: costs actually incurred

Comparing earned values provides important information. By comparing BCWS with BCWP, you can determine any deviations from the schedule (for example, if the project is progressing too slowly). By comparing the BCWP with actual costs, you can determine any cost variances (for example, if the project is too expensive).

You can store earned value analysis in a separate plan version and evaluate it using the structure information system or controlling information system.

Measurement Methods for Progress Value Determination

Measurement techniques determine how the progress value (planned and actual) is calculated.

The following measurement techniques are available in the SAP system:

  • Start/finish rule

  • Estimation

  • Milestone technique

  • Time proportionality

  • Cost proportionality

  • Quantity proportionality

  • Degree of processing (only for activities, only for actual POCs)

  • Secondary proportionality

  • User-defined techniques (user exit)

You define default measurement techniques for each object (WBS element, activity, and project orders) in Customizing. If required, you can overwrite these defaults in the project structures.

The system uses specific weighting factors to summarize progress values in the project structure. One such weighting factor is the project cost plan (recommended here).

You can use POCs as earned values for the results analysis. To do so, choose technique 07, POC method based on project earned value analysis in the results analysis, and enter the plan version of the earned value analysis.

Evaluation of Progress Analysis

Project structure overview diagram with POC and earned value aggregation details, a hierarchy on the left, and a graph showing schedule (SV) and cost variance (CV) trends.

The POC and the earned value are important project key figures. You can analyze them at the level of individual project elements or aggregated for the whole project/subproject. Like other project key figures, progress analysis values are available in the following report types:

  • Structure-oriented report on progress analysis.

  • Drilldown hierarchy report.

  • Report Painter or Report Writer reports.

You can use the structure overview to evaluate the POC and earned value. The system displays the values in line with the project hierarchy. You can use the structure overview to evaluate the POC and earned value in the following configurations:

  • Aggregated

  • Not aggregated

  • Corrected

  • Not corrected

Values in Progress Analysis

From the hierarchical display, you can navigate to a project object in the period breakdown and to the graphical display.

Flowchart showing cost management metrics for project planning and execution, including Planned POC, Actual POC, BCWS, BCWP, ACWP, schedule variance, cost variance, CPI, ETC, and EAC.

How to Perform Progress Analysis

Progress Analysis Configuration

In the progress version, define the control data used to calculate the percentage of completion (POC) and the earned value.

You must first go to Customizing and define a progress version. We recommend using the standard delivered progress version as a reference.

Customizing: Measurement Methods

You then stipulate the measurement methods used to determine the POC. The measurement method consists of a measurement technique prescribed by the SAP system and other parameters, such as a start POC.

For example, the following measurement methods are determined for the start-finish rule technique:

  • 0-100 method, with a start POC of zero

  • 20-80 method, with a start POC of 20

With the estimation technique, you enter the POC manually in the WBS or network.

You enter a maximum POC and short ID. For as long as an activity is not finished (you do not know when it will be finished), the actual POC cannot exceed the maximum POC. The aim of the maximum POC is to ensure that activities that are almost complete are not overvalued. In the case of estimation, we recommend a maximum POC of 80%.

Customizing: Maintain Default Measurement Methods

You can define a standard method for each object type. It is used if no method is maintained in the object itself.

Define the measurement methods to calculate the POC as a default value for the various object types in the Project System.

The settings are defined per controlling area.

The measurement method that you define is a default value, and you can change it in object master data maintenance. The system only displays the measurement method in the detailed data for the object if you maintain a progress version.

Customizing: Measurement Methods for Orders

You cannot define methods in individual orders of any type except networks. You maintain one here, regulating how individual order types are to be handled.

Define the measurement methods used to calculate the POC for the orders assigned to the project. The settings are defined per controlling area.

You cannot change the measurement methods in order master data maintenance.

How to Configure Progress Analysis