It’s time to put what you’ve learned to the test, get 8 questions right to pass this week.
Q1.
What are some of the fields that should be excluded from the input field selection in a scenario for the outbound delivery cancellation use case?
There are 2 correct answers.
A
Consistency Status
B
Ship-From Location
C
Delivery ID
D
Delivery Month
Q2.
In the “Opportunity – Success prediction” use case, what are the opportunity lifecycle status values which are used in the Training dataset?
Choose the correct answer.
A
Complete/Partial
B
Open/Closed
C
Success/Fail
D
Won/Lost
Q3.
In the “Purchase order – Prediction of incomplete delivery” use case, which business object node is used to persist the prediction results for the proposed delivery status and its probability?
Choose the correct answer.
A
Purchase Order – Item
B
Purchase Order – Root
C
Purchase Request – Item
D
Purchase Request – Root
Q4.
What is the purpose of creating a cloud data source in the "Purchase order – Prediction of delivery delay" use case?
Choose the correct answer.
A
To import data into SAP Business ByDesign from the CSV file
B
To create a joined data source
C
To export data fields to MS Excel
D
To assign a work center view to a report
Q5.
What is one of the benefits of the opportunity success use cases?
There are 2 correct answers.
A
Getting a subjectively unbiased prediction of whether an opportunity will be successful
B
Getting an improved sales forecast for closer annual revenue estimation
C
Getting a real-time product availability check to determine the expected delivery date more accurately
D
Getting an indication of late item delivery
Q6.
Which Machine Learning Cockpit use case is provided as SAP delivered content?
Choose the correct answer.
A
Opportunity – Success prediction
B
Sales quote item – Success prediction
C
Customer – ABC classification proposal
D
Customer invoice – Prediction of payment delay
Q7.
In the “Purchase order – Supplier proposal” use case, why are only those purchase order items with the delivery status Finished used for training the model and predicting the supplier?
Choose the correct answer.
A
Because the Supplier field is guaranteed to be filled in the purchase order
B
Because the supplier is most likely to be the right one for the purchase order, as completion of the delivery is confirmed
C
Because the supplier will be paid for completion of the delivery of the purchase order items
D
Because the invoicing status would be Finished
Q8.
Which data source is used in the machine learning cockpit scenario covering the Customer – ABC classification proposal?
Choose the correct answer.
A
Account master data
B
ABC classification master data
C
Product master data
D
Prospect master data
Q9.
In the “Customer – ABC classification proposal” use case, which key field is used to create the joined data source between the “Prediction Result” and “Accounts” data sources?
Choose the correct answer.
A
Account
B
ID
C
Customer
D
Check-out
Q10.