Configuring Make-to-Stock – Process Manufacturing Based on Process Order (BJ8)

Objectives
After completing this lesson, you will be able to:

After completing this lesson, you will be able to:

  • Configure make-to-stock - process manufacturing based on process order (BJ8)

Master Data for Make-to-Stock – Process Manufacturing Based on Process Orders (BJ8)

Required Master Data Scripts

NameDescription
Create Product Master of Type "Raw Material" (BNR)The material or product master contains information about all the physical materials that are procured, produced, stored and sold. It is also used to manage information about services, for example, for buying and selling services in hours.

The material master holds information such as unique material number, name, material type, unit of measure, descriptions, weight and dimensions. This material information is used and stored in transactions such as sales orders, deliveries, purchase orders and goods movements.

As all information for one material is stored centrally, material master information is organized into different views. For example, sales, storage, MRP, costing and accounting.

Some information in each material is specific to particular organizational units. For example, a sales description is specific to a sales unit (known as sales area), a MRP controller is specific to a specific site (known as a plant) or some information might be specific to a storage location.

Create Product Master of type "Semi-Finished Good" (BNS)
Create Product Master of Type "Finished Good" (BNT)
Create Material BOM for Engineering, Production and Sales (BNK)A production bill of material is a formally structured list of the components that make up a product or assembly (part of a product). The list contains the object number of each component, together with the quantity and unit of measure.

A component might be a raw material or a semi-finished material representing an assembly. It is used in an MRP run to calculate material requirements and in transactions such as a production order.

Information is specific to a production site (known as a plant).

Create Resource (3X8)A resource is a means of production and persons involved in a production process that have capacities assigned to them. Resources are divided into resource categories, such as production line, labor, storage.

Using resources, you can: (1) Create a resource network structure to define the sequence of the resources used, (2) Define a resource hierarchy to group resources for evaluation, and (3) Classify the resources to define their suitability for a purpose or use in an operation.

Create Master Recipe (3X9)You can use the master recipe to describe an enterprise-specific process in process industries without relating to a specific order.

Master recipes are mainly used for planning the manufacture of products. However, you can also use them to describe the clean-out or changeover of a production line. Master recipes are used as a reference for process orders as well as the basis for product costing.

Create Production Version (BLD)A production version is the link between a product bill of material (BOM) and the process routing. It determines which alternative BOM is used together with which routing to produce a material or plan a material.

There may be different production versions based on the lot sizes and validity dates.

Configuration Apps for Make-to-Stock – Process Manufacturing Based on Process Orders (BJ8)

Configuration Apps

Note
Configuration apps are the Self-Service Configuration User Interfaces (SSCUIs) in the SAP S/4HANA Cloud, public edition application Manage Your Solution > Configure Your Solution.
Application AreaApplication SubareaConfiguration Item NameConfiguration Item IDConfiguration StepConfiguration ApproachCategoryGlobal, Country Dependent, or Localized
ManufacturingShop Floor ControlMaster Recipe500359Define Profiles with Default ValuesUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlMaster Data for Process Manufacturing500330Define Order TypesUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlMaster Data for Process Manufacturing500330Define Order-Type-Dependent ParametersUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlMaster Data for Discrete Manufacturing500088Define Production Scheduling ProfileUse Configuration Step in Configure Your SolutionOptionalCountry Dependent
ManufacturingShop Floor ControlMaster Data for Process Manufacturing500330Define Production SupervisorUse Configuration Step in Configure Your SolutionRecommendedGlobal
ManufacturingShop Floor ControlRouting500224Stock and Batch Determination for Goods MovementUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlRouting500224Define Task List UsageUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlRouting500224Define Profiles with Default ValuesUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlConfirmation500087Define Single Screen Entry for Confirming Process OrdersUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlMaster Data for Process Manufacturing500330Specify Scheduling ParametersUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlMaster Data for Process Manufacturing500330Define Production Scheduling ProfilesUse Configuration Step in Configure Your SolutionOptionalCountry Dependent
ManufacturingShop Floor ControlWork Center / Resource500223Define Capacity CategoryUse Configuration Step in Configure Your SolutionMandatoryGlobal
ManufacturingShop Floor ControlWork Center / Resource500223Define Task List UsageUse Configuration Step in Configure Your SolutionOptionalGlobal
ManufacturingShop Floor ControlWork Center / Resource500223Determine Person ResponsibleUse Configuration Step in Configure Your SolutionMandatoryGlobal
ManufacturingShop Floor ControlRouting500224Define Default ValuesUse Configuration Step in Configure Your SolutionOptionalCountry Dependent

Define Profiles with Default Values

Description

You use this configuration item to define a collection of default values for master recipes. When creating or changing a master recipe, you have to enter a profile. The values of this profile are proposed as default values in the new recipe or the new recipe objects. You can either accept or overwrite these values.

In a profile, you can specify default values for the following areas:

  • General recipe data such as control keys
  • Increment between operation numbers
Note
  • Profiles can also be maintained within recipe maintenance. In this case, the changes are only valid until you leave the respective recipe.
  • Certain data can also be copied from a material or from a resource to the master recipe. Values that have been maintained in the material or in the resource take precedence over values from the profile.

Actions

  1. Determine the default values that can reduce maintenance work in your company.

  2. Create the respective profiles and maintain the corresponding default values.

Define Order Types

Description

You use this configuration item to assign orders to order types. You have to assign every order to an order type. The order category (= 40, process order) is a fixed setting and cannot be changed. The order categories are predefined in the SAP system and characterize the technical properties of the orders. The order category defines, for example, the transactions you can use to process an order.

The order type defines the following:

  • Order residence time

    You define how long completed orders remain in the SAP system before they are archived.

  • Status management

    An order can run through several statuses. The status controls which business-related operations are permitted with an order.

  • Number assignment

    You have to assign a number range to each order type. If you create a new order type by copying an existing one, you can either keep the number range assignment or choose a different one.

Note
In addition to the general order parameters at client level, there are also parameters at plant level, which you can process in the configuration step under Shop Floor ControlMaster Data for Process ManufacturingDefine Order-Type-Dependent Parameters

Standard settings

Order types are preset in the standard delivery of the SAP System.

Actions

  1. Classify the orders with regard to their defining characteristics (for example, order category or number range).

  2. For each order category, define whether you want to use status management.

  3. If necessary, define your own order types. To do so, copy an existing order type and adjust the data as necessary.

Define Order-Type-Dependent Parameters

Description

You use this configuration item to define the parameters that are valid for each order type and plant.

The parameters are split up as follows:

Master Data

Here, you define the data that influences master data selection or order master data maintenance. The screen contains the following indicators:

  • The production version defines if the production version is selected automatically or manually.
  • The recipe selection ID defines the priorities according to which the recipe is selected.
  • You can activate the entry tool for operations to help you when you create operations.

Planning

General

  • Substitute MRP controller/substitute production supervisor. These are proposed when you create process orders if an MRP controller or production supervisor are not specified in the material master, or if there is no reference to material.
  • Reservation/Purch.Req. specifies whether certain order objects (operations, components) are relevant to MRP.
  • Collective requisition enables collective purchase requisition per orderfor externally processed operations or non-stock items.

Bill of Material

  • Application defines how the BOM alternatives are selected
  • Batch determination
  • Search procedure defines how batch determination is to take place

Quality Inspection

Inspection type defines how a quality inspection is to be carried out

Implementation

  • Status Change Documents
    • Here, you define whether you want change documents to be written if a status change occurs. You also define the level at which the change documents are written:
    • A status change document documents the following:
      • Which status has been changed
      • Who changed the status
      • Whether the status has been activated or deactivated
      • In which transaction the status change has been carried out
    • In the process order, you can define the status at the following levels:
      • Order header
      • Operation
      • Material component
  • Status change documents can thus be defined independently of each other, at each of these four levels.
    Note
    If you have defined these parameters such that status change documents are written for a particular order level, the SAP system only writes a status change document for a status change from this point in time if the order (or operation/component) has been created since the status change documents have been activated.
  • Documentation of Goods Movements

    You can specify that goods movements are to be documented with reference to an order.

Cost Accounting

  • Cost Accounting

    Here, you define the parameters relevant for cost accounting, such as costing variants for planned and actual costs and a results analysis key.

  • Distribution Role

    Default (distribution) role defines an automatically generated distribution role for CO settlement.

Define Production Scheduling Profile

Description

You use this configuration item to create production scheduling profiles for specific plants.

In a production scheduling profile, you can:

  • Specify that certain business transactions or processes are to be carried out in parallel in a production or process order:
    • Order release at the time the order is created
    • Generation of document link from the material master when the order is created
    • Generation of document link from a BOM when the order is created
    • Scheduling upon order release
    • Generation of document link from the material master upon order release
    • Generation of document link from a BOM upon order release
  • Specify whether only partial quantities are to be confirmed at the time of an availability check
  • Specify that an automatic goods receipt is to take place
  • Specify that in the case of the confirmation:
    • No short quantities are to be updated
    • No excess quantities are to be updated
    • Neither short nor excess quantities are to be updated
    • An adjustment of the operation and component quantities to the actual values is to take place
  • Make various specifications in the area of batch management:
    • Automatic batch creation when an order is opened
    • Branching to batch classification when a batch is changed
    • Extended batch classification via Customer Function Call
    • Generation of a batch split record in the production order for each batch that is found
  • Specify settings regarding transport:
    • Specify that only transport requirements are to be created if transport requirements can be generated for all the components of the operation
    • Specify that either the committed quantities or the required quantities are to be taken into account when transport requirements are generated
    • Specify that the creation of transport requirements is to take place automatically
  • Specify which order type is to be suggested depending on the business process
  • You can assign a production scheduling profile to a:
    • Material (Work Scheduling screen in material master)
    • Production supervisor
Note
  • The assignment to a material takes higher priority.
  • The production scheduling profile is adopted in the production or process order at the time the order is opened.

Actions

  1. Create the necessary production scheduling profiles.

  2. Assign the profiles to the appropriate materials or production supervisors.

Define Production Supervisor

Description

You use this configuration item to define the production supervisors for your plants. In addition, you can assign a control profile to each production supervisor. By assigning production supervisors to materials within the application, you can define responsibilities for a material within production activity control.

Actions

  1. Create your production supervisors.

  2. If necessary, assign profiles to your production supervisors.

Stock and Batch Determination for Goods Movement

Description

You use this configuration item to define parameters for the automatic stock and batch determination for each plant, order type, and business transaction. You can assign a stock determination rule and switch off stock or batch determination.

The business transactions for production orders are:

  • Backflushing of components for confirmations
  • Picking
  • Batch determination

Actions

  1. Enter the plant, order type, and business operation.

  2. Enter the type of check (no check, checking rule).

Define Task List Usage

Description

In this configuration item, you can define task list usages to assign routing to various work areas. You can create several task lists with various usages for the production of a material. In work orders, you can assign order types to usages. The system uses the usage in an order for automatic task list selection.

Example

You can specify that a routing is to be used only for plant maintenance or for goods receipt.

Actions

Define task list usages.

Define Profiles with Default Values

Description

You use this configuration item to define a collection of default values for task list headers and operations.

You can minimize the maintenance of task list data as follows:

  • Data from the material master is proposed
  • Data from the work center can be referenced or copied
  • Data from the profile is proposed

You can enter a profile in routing maintenance. The values from this profile are proposed when you create a new routing or routing object, such as a header or an operation. This data can either be saved or overwritten.

Example

The profile contains default values for the status or for the operation increment.

Note
The values you maintained in the material master or the work center will be proposed before any values from the profile.

Actions

  1. Determine the default values that can reduce the amount of maintenance work in your company.

  2. If necessary, define several profiles.

  3. Maintain the default values for routing maintenance.

Define Single Screen Entry for Confirming Process Orders

Description

You use this configuration item to create layouts for the single screen entry of confirmations. You do this by defining the confirmation profile for single screen entry of time ticket confirmations. You can define the layout of the entry screen. When you do this, you define which input and output fields are displayed and in which order. These definitions are saved in the profile.

  • Standard Profile

    With the Standard Prof. indicator, you can define that the profile is to be used as the standard profile. Only one profile each can be defined as standard profile for single screen entry.

  • Area Selection
    • In the header area you can define which data is to identify the operation or phase to be confirmed. Here, for example, you can define whether only the confirmation number and/or order, sequence and operation/phase can be entered.
    • In the detail areas, you define which information can be entered for the operation/phase to be confirmed and in which order the fields in question are displayed. You can select up to seven detail areas, each containing one group of possible entry fields. Note that every input and output field can only be outputted once. When you save, the system automatically checks whether this rule has been adhered to. To carry out this check beforehand, choose the Check area selection button.
    • Titles can be assigned to the detail areas, which are reproduced on the buttons above the corresponding area. You can use these buttons to open and close the areas. This means that the number of fields on the screen can be kept to a minimum. With the Closed indicator you define that the area is to be closed when the function is first called up.
    • You can display a preview of the individual area and also of the entire entry screen. To do this, choose the corresponding button (Header area preview, Detail area preview, List screen preview)
  • Defaults
    • Confirmation function

      You define whether a partial confirmation, final confirmation, or final confirmation with posting of open reservations is to be proposed.

    • Default value
      • You can define the time of default determination for quantities and/or activities:
        • No proposal
        • Immediate proposal
        • Proposal when saving
      • For default determination:
        • The quantity that is still to be confirmed is calculated
        • The activities are calculated in proportion to the quantities

Actions

For the activities, you can define 6 texts that are displayed during confirmation entry. These texts are overwritten with the texts from the standard value key in the work center after you have chosen Enter. If you want to prevent this from happening, set the indicator Fix text. You can hide activities for which you do not want to enter a confirmation by setting the indicator Hidden.

Note
The texts entered for the buttons in the detail area and for the activities are saved in the logon language.

Specify Scheduling Parameters

Description

You use this configuration item to define the parameters for scheduling process orders per plant, order type, and production supervisor. This comprises maintaining detailed scheduling, date adjustment when dates are exceeded, scheduling control for detailed scheduling, and reduction.

  • In Detailed Scheduling you specify:
    • How production dates are determined
    • Whether capacity requirements are generated
  • In Adjust Scheduling you specify whether and how basic dates are adjusted to the production dates (for example, when deadlines are exceeded) and where the dates for the dependent requirements are meant to be.
  • In Scheduling control for detailed scheduling you specify the control parameters for detailed scheduling, among others
    • Scheduling Type

      Here you specify the scheduling direction and whether scheduling is to be carried out to specific points in time. You can also specify that a scheduling run is only to be used to generate capacity requirements.

    • Start Date in the Past

      Here you specify how many days an order may lie in the past before today's scheduling is automatically triggered.

    • Automatic Scheduling

      Here you can specify whether scheduling is automatically executed on saving if changes relevant to scheduling have occurred.

    • Automatic Log

      Here you specify whether the log is automatically displayed after scheduling.

    • Scheduling with Breaks

      Here you specify that the times of a break are to be taken into account.

    • From Production Dates

      Here you specify that when creating or changing an order the user must enter the scheduled dates (production dates) instead of the basic dates.

    • Shift Order

      Here you specify whether the order can be moved if partially confirmed operations exist.

    • Latest Staging Date

      Here you specify where the required date of a component is to be in relation to the operation.

  • In Reduction you specify
    • Up to what maximum reduction level the reduction takes place
    • To what percent the floats before and after production in every reduction level are to be reduced

Actions

Define the scheduling parameters for process orders.

Define Production Scheduling Profiles

Description

You use this configuration item to create production scheduling profiles for specific plants. The production scheduling profile is adopted in the process order at the time the order is opened.

In a production scheduling profile, you can:

  • Specify that certain business transactions or processes are to be carried out in parallel in a process order
    • Order release at the time the order is created
    • Scheduling of the order when it is released
  • Specify whether only partial quantities are to be confirmed at the time of an availability check
  • Make various specifications in the area of batch management:
    • Automatic batch creation when an order is opened
    • Branching to batch classification when a batch is changed
    • Extended batch classification via Customer Function Call
  • Specify settings regarding transport:
    • Specify that only transport requirements are to be created if transport requirements can be generated for all the components of the operation
    • Specify that either the committed quantities or the required quantities are to be taken into account when transport requirements are generated
    • Specify that the creation of transport requirements is to take place automatically
  • Specify that in the case of the confirmation:
    • No short quantities are to be updated
    • No excess quantities are to be updated
  • Specify which order type is to be suggested depending on the business process

You can assign a production scheduling profile to a:

  • Material (Work Scheduling screen in material master)
    Note
    The assignment to a material takes higher priority.
  • Production supervisor

Actions

  1. Create the necessary production scheduling profiles.

  2. Assign the profiles to the appropriate materials or production supervisors.

Define Capacity Category

Description

You use this configuration item to assign several capacities belonging to different categories to one work center.

Capacity categories can be, for example:

  • Machine
  • Labor
  • Setup crew
  • Emissions

You must maintain the available capacity for every capacity category (for example, shift start, shift end, calendar, and so on). You can maintain default values for this data per plant and capacity category.

Actions

Define which capacity categories are to be available.

Define Task List Usage

Description

You use this configuration item to specify the tasks lists in which a work center may be used. You can, for example, categorize work centers into maintenance work centers or inspection work centers according to their relevance and their usage in maintenance plans or inspection plans. You can also allow multiple, cross-application uses in any combination.

Actions

  1. Define the usage key.

  2. Assign the task list type to the usage key.

Determine Person Responsible

Description

You use this configuration item to determine a person or group of people responsible for maintaining the master data in certain work centers. These employees are not responsible for planning tasks but only for the maintenance of the work center parameters.

Actions

Define the people responsible for your work centers.

Define Default Values

Description

You use this configuration item to specify which data is contained in an operation that is automatically created during order creation. Within order creation, you can determine that an operation is created automatically if no routing exists for the material to be produced or no routing can be selected.

The automatically created operation should contain the following data, for example:

  • Control key

    The control key specifies how an operation is processed (for example, whether it is scheduled, costed, and so on)

  • Operation number
  • Operation short text
  • Material group (only for external processing)
  • Work center where the operation is carried out

Actions

Specify the data for operations automatically created by the system.