Applicable Process Steps
Process Step | Description |
---|---|
Create Planned Independent Requirements | This process step shows you how to use planned independent requirements (PIR) to perform demand management functions. A planned independent requirement contains one planned quantity and one date, or a number of planned independent requirements schedule lines, meaning one planned quantity split over time, according to dates. |
Material Requirements Planning | This process step shows you how to use material requirements planning to tailor available capacities and receipts on time to suit requirement quantities. You can use MRP or consumption-based planning for this purpose. |
Evaluate the Stock / Requirements Situation | This process step shows you how to monitor the material coverage situation for material after the requirements planning has been carried out. |
Create Production Order | This process step shows you how to create production orders. Because the order release is executed automatically, production can start immediately. |
Review Production Order | This process step shows you how to review the created production orders. |
Goods Issue of Batch-Managed Components | The withdrawal of the raw materials is used for the order. This withdrawal can be done by using the picking list or doing a manual goods issue. If the material is set for backflush (in material master or resource), the withdrawing is done automatically after you confirm the operation or the whole order. Backflushing should not be used for batch-managed components (to ensure that the physically picked and consumed batch is the same as the recorded batch). |
Goods Issue via Pick List | The released production order is now ready for picking. This process step shows you how to use the pick list to move all materials to the production storage location can be issued to the order. |
Manage Goods Issue (instead of Picking List) | This process step shows you how the system performs a goods issue. |
Monitor Order Progress | This process step shows you how to generate a worklist for production orders, components and operations, with user-specific selection and layout settings. |
Post Goods Receipt for Order | This process step shows you how to post the goods receipt for the production order. You may post goods receipt for the total quantity, but usually already partial quantities of the products are required for further processing, such as consumption for further production or subsequent deliveries for sales orders. |
Confirm Production incl. Component Backflush | In the process industry, GR and GI postings are usually done immediately during the physical movements of the materials to ensure batch traceability and data consistency. Order confirmations with backflush are done at shift end or day end. The sum of the GI and GR quantity for the given order is then recorded within the confirmation and scrap quantities (optional). The time ticket confirmation allows recording either the default times for machine and labor usage, or record actual times for major deviations. |
Review Production Order Confirmation | This process step shows you how to review confirmations for the orders. |
Review Scrap Report | This process step shows you how to review confirmations for the orders. |