Locate Scope Item in LoB

The Scheduling Agreements in Procurement (BMR) scope item belongs to the Operational Procurement business area, which is part of the Sourcing and Procurement line of business.
Introduction
This scope item supports the scheduling agreement in the procurement process.
The use of scheduling agreements can shorten processing times and reduce the amount of paperwork you are faced with. One delivery schedule can replace many discrete purchase orders or contract release orders. Delivery of the total quantity of materials specified in a scheduling agreement item is spread over a certain period in a delivery schedule, consisting of lines indicating the individual quantities with their corresponding planned delivery dates. Inventories can be reduced to a minimum. You can perform your manufacturing operations on the Just-in-Time (JIT) principle. Your suppliers require shorter lead times. Smaller deliveries are required, which can be spaced out over a longer period. Delivery scheduling enables suppliers to plan and allocate their resources more efficiently.
A scheduling agreement is a long-term outline agreement between vendor and ordering party over a predefined material or service that is procured on predetermined dates over a framework of time.
Usage of Scheduling Agreements
While using scheduling agreements, you can work with or without release documentation. You can see in the following table information about both scheduling agreements with or without release documentation.
Without release documentation | With release documentation |
---|---|
The delivery schedule lines have official character, that is, they are transmitted to the vendor as they are saved in the system. The system does not document in detail releases against the scheduling agreement that have been sent to the vendor. Therefore, in the case of the document type without release documentation, the message control facility should be set up in such a way that a message is immediately sent to the vendor if any changes are made to the delivery schedule stored in the system. All open scheduling agreements are always output. | If you use scheduling agreements with release documentation, the delivery schedule lines are not transmitted directly to the vendor. Initially, the lines of the delivery schedule stored in the system for an LPA scheduling agreement are for internal information only. A message informing the vendor of your material requirements cannot be transmitted to the vendor until you explicitly create an SA release, that is, a forecast (FRC) or Just-in-Time (JIT) delivery schedule. Through this process, you can change the way the schedule lines are represented. With the release documentation, you can display the SA releases (delivery schedules) transmitted to a vendor over a certain period at any time. This enables you to trace precisely when you sent which information to the vendor. |
Process Overview

The figure, Scheduling Agreements in Procurement - Standard Procurement Process Overview, shows the process diagram for Scheduling Agreements in Procurement – Standard Procurement.

The figure, Scheduling Agreements in Procurement - Consigned Procurement Process Overview, shows the process diagram Scheduling Agreements in Procurement – Consigned Procurement.

The figure, Scheduling Agreements for Procurement with EDI Integration, shows the process diagram of Integration of Scheduling Agreement for Procurement with External Suppliers.
Creating a Scheduling Agreement
You can create a scheduling agreement as follows:
- Manually
- You enter all data on the scheduling agreement manually.
- Using a reference : As reference document (the document you copy from), you can use:
- Purchase requisitions
- RFQs/quotations
- Other scheduling agreements
- Centrally Agreed Contracts
If you wish to set up a scheduling agreement not with one of your vendors but with one of your own plants, you should create a stock transport scheduling agreement (scheduling agreement for longer-distance stock transfers).
Business Benefits
Key Process Flows
The following are the key process flows of scheduling agreements in procurement:
Create or change a scheduling agreement.
Maintain a delivery schedule.
Maintain a quota arrangement.
Release a scheduling agreement.
Post a goods receipt.
Create a supplier invoice.
Manage Purchase Scheduling Agreement

With this app, you can view, edit, create, delete, and release scheduling agreements. You can maintain supplier- and material-specific scheduling agreements along with schedule lines. This app also displays scheduling agreements that are soon to expire and provides a way to renew or create new scheduling agreements.
This app uses the SAP_BR_PURCHASER business role. You can:
Display scheduling agreements based on search criteria such as agreement ID, editing status, status, supplier, agreement type, purchasing organization, and validity period.
Display scheduling agreements such that the ones that are soon to expire appear at the beginning of the search results.
Create a scheduling agreement manually by selecting a document type. While creating a new scheduling agreement, you can choose to do the following:
Enter delivery details, validity period, and payment terms.
Add a new item and enter the net order price if it is not maintained.
Enter information related to handling, GR/IR control, scheduling control, cumulative quantity, account assignment, delivery, output control, and schedule lines.
- Withdraw a purchase scheduling agreement from approval. You can then make the required changes to the purchase scheduling agreement and submit it again for approval.
Add attachments.
Define supplementary conditions in the application UI.
Display the output details for scheduling agreements. If the scheduling agreement is created using this app, the output appears in PDF format.
Apply new condition types to add a new condition type to an existing date range or to create a new date range.
Release of a delivery schedule is possible at the item level and at the scheduling agreement level.
Release the schedule lines to the supplier that contains finalized information for the supplier regarding quantities and delivery dates.
Note
When you choose Release on the list page, this application launches the UI screen. You can select a release type such as Generate Forecast Schedule, Generate JIT Schedule, or both. Once you select a release type and choose Release, you can see the Release Result Log that displays the details of delivery schedules.
In cases where the flexible workflow is activated, you can release the schedules only when the scheduling agreement is finally approved.
View the release documents for a release schedule either through the quick view or access the item and view complete details.
Assign a scheduling agreement item to several accounts. You can define how the quantity and value of the scheduling agreement items are distributed to individual account assignment items. Multiple account assignments are supported for the scheduling agreement document. The account assignments are distributed on a quantity and percentage basis. The partial invoice for the document can be derived from account assignment category, distributed in sequence or distributed proportionally.
- Create a copy of the existing conditions of the scheduling agreement document. However, Copyis active only when you are in Edit mode. Some of the scenarios for copy conditions are:
- Base condition without any supplementary condition: In this case, the purchaser is able to select the existing base condition and copy to a new validity period. You can manually edit the amount field accordingly.
Note
You cannot copy an individual supplementary condition that is not part of any base condition. - Copying a base condition that has a supplementary condition: In this scenario, the purchaser is able to copy the base condition along with the supplementary conditions. You can copy an existing validity period to create a new validity period.
- You cannot select and copy multiple validity periods at the same time. Multiple conditions under the same validity period can be copied.
- Base condition without any supplementary condition: In this case, the purchaser is able to select the existing base condition and copy to a new validity period. You can manually edit the amount field accordingly.
Mass Changes to Purchase Scheduling Agreements

With this app, you can apply mass changes to fields in your scheduling agreements at the header and item level. This allows you to implement changes that affect a large number of your scheduling agreements. Whether you need to change payment terms or exchange rates at the header level, a delivery address or shipping instructions at the item level, or even partner data – in multiple scheduling agreements – this app lets you do this with just a few clicks. You can:
- Display a list of your scheduling agreements based on a range of filter criteria such as supplier, purchasing organization, purchasing group, and material.
- Display the headers and items of your scheduling agreements separately on two different tabs.
- Select the scheduling agreement headers and/or items that you want to change.
- Specify whether you want to clear, replace, or keep values in the fields.
Note
You can enter only one value per field. - View the status of mass change jobs that you have scheduled for scheduling agreements
Note
You can also monitor the status of your jobs directly by using the Monitor Mass Changes - Purchase Scheduling Agreements app. As of release SAP S/4HANA Cloud 2002, this app has been renamed from Monitor Mass Changes - Scheduling Agreements to Monitor Mass Changes - Purchase Scheduling Agreements. - Adapt the views to display precisely the data you need.
SAP Fiori Apps
The following table lists the SAP Fiori apps that are used in the Scheduling Agreement with Release Doc for Standard Procurement Process steps:
Process Step | Business Role | SAP Fiori App |
---|---|---|
Creating Scheduling Agreement w/ Release doc - Standard | Purchaser | Manage Purchase Scheduling Agreements |
Mass Changes to Purchase Scheduling Agreements (Optional) | Purchaser | Mass Changes to Purchase Scheduling Agreements |
Maintaining Delivery Schedule | Purchaser | Manage Purchase Scheduling Agreements |
Creating Scheduling Agreement w/ Release doc - Standard | Purchaser | Manage Purchase Scheduling Agreements |
Maintaining Quota Arrangement | Purchaser | Manage Quota Arrangements |
Creating Planned Independent Requirements | Production Planner | Maintain PIRs |
MRP Run for Single Item | Material Planner - External Procurement | Schedule MRP Runs |
Evaluating Stock/Requirements Situation | Material Planner - External Procurement | Monitor Material Coverage - Net / Individual Segments |
Displaying Delivery Schedule | Purchaser | Manage Purchase Scheduling Agreements |
Checking the allocated Quantity in Quota Arrangement | Purchaser | Manage Quota Arrangements |
Printing Scheduling Agreement | Purchaser | Manage Purchase Scheduling Agreements |
Releasing Scheduling Agreement | Purchaser | Manage Purchase Scheduling Agreements |
Printing Scheduling Agreement Releases | Purchaser | Manage Purchase Scheduling Agreements |
Checking Scheduling Agreement Release Documentation | Purchaser | Manage Purchase Scheduling Agreements |
Evaluating the Stock/Requirement Situation | Material Planner - External Procurement | Monitor Material Coverage - Net / Individual Segments |
Posting Goods Receipt | Warehouse Clerk | Post Goods Movement |
Creating Supplier Invoice with Scheduling Agreement/GR Relation | Accounts Payable Accountant | Create Supplier Invoice |
The following table lists the SAP Fiori apps that are used in the Scheduling Agreement Without Release Doc for Standard Procurement Process steps:
Process Step | Business Role | SAP Fiori App |
---|---|---|
Creating Scheduling Agreement w/o Release doc - Standard | Purchaser | Manage Purchase Scheduling Agreements |
Approving Scheduling Agreement (Optional) | Purchasing Manager | My Inbox - All Items |
Maintaining Delivery Schedule | Purchaser | Manage Purchase Scheduling Agreements |
Printing Scheduling Agreement | Purchaser | Manage Purchase Scheduling Agreements |
Evaluating the Stock/Requirement Situation | Material Planner - External Procurement | Monitor Material Coverage - Net / Individual Segments |
Posting Goods Receipt | Warehouse Clerk | Post Goods Movement |
Creating Supplier Invoice with Scheduling Agreement/GR Relation | Accounts Payable Accountant | Create Supplier Invoice |
The following table lists the SAP Fiori apps that are used in the Integration of Scheduling Agreement for Procurement with External Suppliers Process steps:
Process Step | Business Role | Fiori App |
---|---|---|
Create Scheduling Agreement w/ Release doc - Standard | Purchaser | Manage Purchase Scheduling Agreements (F2179) |
Maintain Delivery Schedule | Purchaser | Manage Purchase Scheduling Agreements (F2179) |
Print Scheduling Agreement | Purchaser | Manage Purchase Scheduling Agreements (F2179) |
Release Scheduling Agreement | Purchaser | Manage Purchase Scheduling Agreements (F2179) |
Check Scheduling Agreement Releases | Purchaser | Manage Purchase Scheduling Agreements (F2179) |
Send Forecast and JIT Delivery Schedule – EDI relevant | Automated | Automated |
Check Forecast and JIT Delivery Schedule in AIF (Message Dashboard) | Configuration Expert - Business Network Integration | Message Dashboard |
Check Incoming Inbound Delivery in AIF (Message Dashboard) | Configuration Expert - Business Network Integration | Message Dashboard |
Review Inbound Delivery Document in Scheduling Agreement Document | Purchaser | Display Scheduling Agreement (ME33L) |
Post Goods Receipt for Inbound Delivery | Receiving Specialist | Change Inbound Delivery (VL32N) |
Check Incoming Invoice in AIF (Message Dashboard) | Configuration Expert - Business Network Integration | Message Dashboard |
Review Supplier Invoice | Accounts Payable Accountant | Supplier Invoices List (F1060A) |
Configuration Apps
In Sourcing and Procurement, several Self-service Configuration UIs (SSCUIs), also referred to as configuration steps, are available in the Manage Your Solution app. The following SSCUIs affect the area of scheduling agreements in procurement process:
Organization | ||
---|---|---|
Define Mapping of Material Groups to Purchasing Group | Define Shipping Data for Plants | Organizational Structure |
Plants | Purchasing Organizations | Storage Locations |
Scheduling Agreement Processing | ||
---|---|---|
Activate Flexible Workflow for Purchase Scheduling Agreements | Maint. Rel. Creation Profile for Sched. Agmt. w. Rel. Docu. |