Introducing the SAP Project System (SAP PS) Structures
Introducing the SAP Project System (SAP PS) Structures
Introducing SAP S/4HANA EPPM Project System
5 mins
Introducing the User Interface
50 mins
Identifying Requirements for Structures in the SAP Project System (SAP PS)
20 mins
Quiz
Customizing Work Breakdown Structures (WBS)
Customizing Activities and Networks
Working with Project and Simulation Versions
Knowledge quiz
It's time to put what you've learned to the test, get 8 right to pass this unit.
1.
The SAP Fiori UX is only available for expert users.
Choose the correct answer.
True
False
2.
A project can only be created directly element by element.
Choose the correct answer.
True
False
3.
Which object can be divided into sections?
Choose the correct answer.
Spaces
Pages
Groups
Catalogs
4.
You can connect a network activity to several WBS elements.
Choose the correct answer.
True
False
5.
SAP PS is a component of both SAP PLM and SAP ERP.
Choose the correct answer.
True
False
6.
The long-term goal of the SAP UX strategy is to offer only major business and analytic applications on SAP HANA SAP Fiori as the unified UI.
Choose the correct answer.
True
False
7.
The SAP GUI is still available in S/4HANA as an alternative navigation option.
Choose the correct answer.
True
False
8.
What are examples of types of project that SAP EPPM Project System supports?
There are two correct answers.
Investment projects
SAP Customer Experience
IT projects
Croos-Application Time Sheet
9.
What does a hierarchical project structure enable?
Choose the correct answer.
Slice-and-dice cost allocations
Easy cost planning
The integration to Controlling
Top down and bottom up estimates