Creating Networks
Note
See the following video to learn more about the creation of networks:Network Structure
In the SAP system, the network is a special work order that uses a common structure with production or maintenance orders, for example. Each network has a unique identification assigned automatically by the system, depending on the network type (internal number assignment) or by the user when creating the network (external number assignment).
The network header of a network contains default organizational assignment data and control data that applies to the entire network (similar to the project definition for WBS elements). You can assign a network to a work breakdown structure or a sales order in the network header.
Activities form the basis for planning and executing networks. Each activity can be assigned to any WBS element (if it is an account assignment element). The network is scheduled at the activity level. Relationships determine the order in which activities are carried out. Consequently, relationships – and the duration of the activities – are essential for scheduling networks. You use activity elements to split activities into more detail or to enhance them.

Relationships
Networks can be header-assigned or activity-assigned, depending on order type or plant. Normally, activity-assigned networks are used to gather costs for each activity. Header-assigned networks are only significant for assigning networks to sales orders (without WBS).
The SAP Project system has the following activity categories:
Internally processed activities contain a work center at which the work is to be carried out. They include the working time and the duration of the activity. The assignment of the work center to a cost center provides an activity type and a rate so that planned costs can be calculated for the activity.
External activities are used for procuring activities or services not procured within your company. Purchase requisitions are generated for externally procured activities that are processed in Purchasing. A differentiation is made between "external processing" and "service" for externally procured activities.
, General costs activities, enable you to plan costs other than internal or external activities. For example, you can plan expenses or insurance costs using general costs activities.
Activity Organization
Normally, activities are not organized randomly in a network. There are usually technical or content-stipulated dependencies between the activities. Relationships determine the chronological sequence of the individual activities in a network (or standard network) or different networks. You can enter additional data (such as a time interval of the relationship or reference to a particular factory calendar) in the detail screen for each relationship. The type of relationship defines how the individual activities are linked to each other.

Activities
Activities can be described as follows:
The activity Assembly begins with the end of the predecessor activity Production.
The activityPurchase order begins with the start of the activity Engin./Design.
The activity Work Scheduling ends with the end of the activity Engin./Design.
The activity Test Run ends with the start of the activity Approval.
In addition, you can define time intervals for the relationships, allowing you, for example, to control that the activity Assembly begins two days after the end of the activity Production, or that the activity Purchase order begins if the planned 20% of the design phase has been completed.
Network Structure Graphic
In the network structure graphic, you can display relationships "time-dependently" to illustrate the logical process chain. All relationships in the network structure graphic are displayed as FS relationships by default. You can access the network structure graphic from various transactions in the SAP Project System, such as the Project Builder, Scheduling, or the structure info system. The network graphic provides all the functions needed to process a network, such as activity or relationship insertion. The cycle analysis is a function that you can perform only in the network structure graphic. A cycle is a closed sequence of relationships and activities ("closed" means that when you start from one activity, you end up back at the same activity with relationships). If the activity-relationship-activity path is cyclical, you cannot schedule the network. Cycle analysis is a tool that enables you to detect and correct cyclical relationships.
