The multiple counter plan recognizes the following scheduling parameters:
Cycle modification factor:
The cycle modification factor can lengthen or shorten the maintenance cycle in the multiple counter plan.
Preliminary buffer:
Defines the call date for the maintenance order in relation to the calculated planned date and thereby also the basic start date.
It's specified in days.
Operation type:
Determines the type of link for the maintenance cycles. If the AND link is used, the order is only created when all the cycles are due. For an OR link, the order is created as soon as one of the cycles is due.
Start date/start time:
Defines the start date for automatic starting of the maintenance plan using deadline monitoring.
Scheduling period:
Defines the period for which the system calculates in advance planned dates/calls, which can then be displayed in a scheduling overview.
Completion requirement:
Defines that the current call object must be completed before a new one is generated.
Shift factors:
Define the percentage of the shift to be applied to the calculation of the next date.
Tolerances for shift factors:
Determine the time span in which positive/negative variances between actual and planned date don't influence subsequent scheduling.
Multiple Counter Plan and Time Zones
When you process or display maintenance plans of type Multiple Counter in the Manage Maintenance Plansapp (F5325), you can view the scheduling start date and time in your local user time zone. The system converts the system time zone into the time zone of the current user as set in the SAP Fiori Launchpad and the browser.