Creating Master Data for Service with Advanced Execution

Objective

After completing this lesson, you will be able to create master data for Service with Advanced Execution

The Creation of a Work Center

In this lesson, we discuss the use of work centers in Plant Maintenance and scenario's like Service with Advanced Execution.

Use and Function of Work Centers

Examples of maintenance work centers are welders, metalworking and also mechanics.
  • A work center is an organizational unit that defines where and when an operation can be performed.

  • Work centers can represent machines or people.

  • Work center can be used as responsible maintenance work centers.

  • Work centers can be used to execute operations.

Work Center Data

Work center data is used for the following business functions:

  • Basic data:

    Contains the description, work center category and task list usage.

  • Default values:

    For example, a default control key.

  • Capacity:

    Available capacity is usually entered as the standard available capacity with the specifications – factory calendar, work start and end, level of individual capacity (number of people), and operating time per capita. The available capacity can be restricted according to time or can be organized in shifts differing from the standard available capacity.

  • Scheduling:

    Start and end of an operation are calculated on the basis of lead times (duration of operation) The work center contains a reference to the duration field in the operation.

  • Costing:

    Internal personnel costs are calculated on the basis of the activity types defined in Controlling. The activity types contain the assignment to an hourly rate. Activity types are assigned indirectly using a cost center, not directly to the work center.

  • Personnel data:

    In addition to defining available capacity, people (personnel numbers from human resources) or positions can be assigned in the work center.

Note

Business Functions LOG_EAM_SIMPLICITY_19 (Web) and LOG_EAM_CI_19 (SAPGUI) offer a work center extension.

You can enter the following new default values in the work center:

  • Contract and Contract Item

  • Supplier

  • Purchasing Group

  • Purchasing Organization

  • Material Group Hierarchy Node

  • Material Group

Maintaining a Work Center

In SAP S/4HANA, there are different ways to create a work center, depending on how the integration with Human Resources (HR) and the Business Partner is to be handled.

There are generally two ways of creating a work center:

  • Variant A: No business partner integration

    Use a work center with or without HR integration (organizational unit or position/employee).

  • Variant B: HR / With business partner integration

    • Create a personnel number with business partner Integration (via transaction PA40) .

    • Assign position / personnel number to work center.

Capacities

Note

See the following video to learn more about capacities in SAP S/4HANA:

How to Customize a Work Center

Create Master Data for Service with Advanced Execution