Confirmations are the premise for progress control and the basis for cost charging of internal activities performed for the production order. For this reason, confirmations are carried out by the shop floor workers as promptly as possible. You can confirm individual operations or entire orders. Due to the different requirements that arise in practice, SAP offers several different options for posting confirmations.
Confirmation Options

Depending on your business requirements, the system offers various variants for order confirmation:
Production order confirmation on order header level
In this scenario, you enter a confirmation for the entire order. If you enter a confirmation on order header level, the system confirms all operations that have a control key in which confirmation is possible or required. The quantities confirmed in the operations are proportional to the quantities confirmed in the order header. You can either confirm the order in one confirmation posting or post multiple order confirmations until the order quantity is reached. After posting an order confirmation, the system sets respective confirmation statuses on order header and operation level.
Time ticket confirmation
In this scenario, you enter a confirmation for each (confirmation relevant) operation in the order. Similar to the previous case, you can either confirm each operation in one confirmation posting or post multiple operation confirmations until each operation of the order is fully confirmed. After posting an operation confirmation, the system sets a respective confirmation status on operation and order header level.
Milestone confirmation
In this scenario, you also confirm the order on operation level. However, by assigning a respective control key to the operations, you define some of the manufacturing operations as milestones. You must only post confirmations for milestone operations. At the same time, the system automatically confirms the non-milestone operations that lie in between the milestones.
Time event confirmation
In this scenario, you confirm time events (for example setup start, setup finish, processing start, processing finish, and so on) for each operation. The system calculates the duration based on the time difference between the start and end event of the respective operation segment. For example, the setup duration is the time between the setup start and the setup finish time event, respectively.
After posting the confirmation, the order and operation status values are updated to either partially confirmed (PCNF) or confirmed (CNF). An order is partially confirmed if at least one but not all of the operations that require confirmation are confirmed (operation status PCNF or CNF). An order is also partially confirmed if all the operations requiring confirmation are finally confirmed, but there are confirmable operations that are partially confirmed. An order is finally confirmed when all operations for which confirmation is required are finally confirmed (status CNF) and when there are no confirmable operations that are partially confirmed (status PCNF).
Example of an Operation Confirmation

In the figure, an example of an operation confirmation and the effect of the confirmation posting to the order is displayed. When confirming the operation, you provide, for example, the following information:
Operation quantities: Yield, scrap, and rework
The yield quantity is the number of partially manufactured items, which are produced during this operation and can be transferred to the next work center. The scrap quantity is the number of partially manufactured items that had to be scrapped when you executed this operation. If required, you can provide additional information in text form or even create quality notifications. The rework quantity is the number of partially manufactured items that cannot be transferred to the next manufacturing operation due to, for example, quality reasons. After you've executed the repair, the respective items reenter the planned production flow.
Actual dates
You enter the actual start and finish date of an operation, which can be used for analysis purposes or rescheduling of subsequent production operations.
Operation activities
You enter operation activities, for example, setup time, machine time, labor time, and so on, to confirm how much time effort is invested into the operation. For each operation activity, the system calculates the respective costs using information maintained in the work center and charges these internal activities to the order.
If configured, for example, in the operation control key, the confirmation also triggers the automated goods receipt of the manufactured items. The goods receipt quantity corresponds to the yield quantity. Furthermore, if components are marked as backflushed, the confirmation triggers the goods issue posting of the respective components. The goods issue quantity corresponds to the sum of all three operation quantities multiplied by the number of components required for the manufacturing of one item. In our bike example, posting a yield of five bikes consumes 10 wheels and five frames, respectively.
Note
Refer to the course with course code S4C40, which is a prerequisite for this course, if you want to learn more about production order confirmation.
For more details about the complex topic of confirmations, refer to the SAP application help.
Prerequisites for Confirmations
Regardless of the confirmation option you select, confirmation parameters must be defined in the configuration activity Define Confirmation Parameters for each order type and plant in order to be able to post confirmations.
To be able to use user-specific layouts for time ticket confirmations, you must set up confirmation profiles in the configuration activity Define Single-Screen Entry for Confirming Production Orders.
For an operation to be confirmed, the control key for the operation must be set accordingly. The control keys contain information whether an operation is a milestone operation, or whether an operation must, can, or cannot be confirmed. The control keys are defined in the configuration activity Define Control Keys.