There are several steps to complete in a user acceptance test.
After you have completed the build for Iteration 1, meet with the customer and demo the stage site to them. Walk the customer through how to complete Customer Stage Site Testing, utilizing the Recruiting Marketing/Career Site Builder workbook.
Note
Remind the customer that the purpose of this phase is to confirm that the site was built to the agreed-upon specifications.After the meeting, send the customer the workbook. Direct the customer to note where there are issues: where the site has not been set up according to the requirements in the workbook, or based on expectations, where things can change.
Direct the customer to enter an "X" in the IT1 column if changes are made, and highlight the cells that were updated. Optionally, they can add a comment. If there are multiple changes during one iteration, use comments.

Iteration 1 Completion
- Iteration 1 must be finalized before the building of Iteration 2 can begin.
- Review the workbook and testing findings from Iteration 1 with the customer.
- Complete the issue revisions and any Iteration 1 changes to the site.
- If there are pages which were not completed (such as additional category or content pages, branded pages, and so on) as part of Iteration 1, complete those pages.
- Ensure that the site setup is complete, such as Real Time Job Sync, Recruiter SSO, Mobile Apply, branding, and so on.