It’s time to put what you’ve learned to the test, get 6 questions right to pass this unit.
Q1.
Which of the following are available in the initial SAP Activate Community Page?
There are 4 correct answers.
A
Information on implementation roadmaps
B
Blogs on SAP Activate topics
C
Latest SAP Activate content updates
D
Resources for SAP Activate project deployments
Q2.
A burn-down chart is used to mark day-by-day how much remains of the scheduled work.
Choose the correct answer.
A
True
B
False
Q3.
Which of the following statement are the true regarding the SAP Activate Community?
Choose the correct answer.
A
It provides information only on Cloud deployments.
B
It provides information only on premise deployments.
C
It provides information on both premise and Cloud deployments.
Q4.
Scrum Board is a tool that helps teams make Sprint Backlog items visible. The board can take many physical and virtual forms but it performs the same function regardless of how it looks.
Choose the correct answer.
A
True
B
False
Q5.
Which of the following statements about Scrum is correct?
Choose the correct answer.
A
In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
B
In Scrum, the team is self-organized, define all task necessary for all project life cycle.
C
The three ceremonies are Sprint Planning, Daily Scrum, Sprint Review (Retrospective).
D
Scrum Master defines and prioritizes features and gathers requirements.
Q6.
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation?
There are 3 correct answers.
A
Defining organizational structure
B
Adjusting predelivered master data for workshops
C
Creating sample transactional data for workshops
D
Adjusting custom code objects
E
Writing Technical Design Documents
Q7.
In the context of Scrum, which of the following statements are correct?
There are 2 correct answers.
A
Product Backlog is a list of features prioritized by business value, the items come from diverse sources, including the Scrum team.
B
Sprint backlog is a subset of Product Backlog loaded onto the Sprint’s timebox. It's the list of work the team is addressing during the current Sprint.
C
Burndown Chart Provides visibility into the Product Backlog, illustrate progress by the team, work is in horizontal and time is in the vertical.