It’s time to put what you’ve learned to the test, get 8 questions right to pass this unit.
Q1.
Which technology is used by the Project Schedule app?
Choose the correct answer.
A
ABAP
B
JAVA
C
UI5
D
WebDynpro
Q2.
You can prevent users from maintaining the overall budget for a project by assigning appropriate user statuses.
Choose the correct answer.
A
True
B
False
Q3.
Settlement rules determine, in part, which portions of the sender’s costs are transferred to which cost receivers.
Choose the correct answer.
A
True
B
False
Q4.
Which of the following cost planing methods allows for the distribution of costs over several periods?
There are 2 correct answers.
A
Overall planning
B
Cost element planning
C
SAP BPC
D
Unit costing
Q5.
You can use the planned costs to check the budget and assigned funds.
Choose the correct answer.
A
True
B
False
Q6.
During the project planning phase, you can plan costs for materials, activity allocations, services, and overheads with Easy Cost Planning (ECP) for WBS.
Choose the correct answer.
A
True
B
False
Q7.
Budgeting in the SAP Project System (SAP PS) is not just a single transaction, but a process that involves various transactions. Which of the following transactions refer to budgeting in SAP PS?
There are 2 correct answers.
A
Maintain Original Budget
B
Transfer Budget
C
Convert Budget
D
Increase Budget
Q8.
Settlement rules are stored in the sender objects and contain distribution rules and settlement parameters.
Choose the correct answer.
A
True
B
False
Q9.
Which of the following are examples of period-end closing procedures?
There are 2 correct answers.
A
Overhead distribution
B
Outgoing orders
C
Cost forecast
D
Progress analysis
Q10.
Cost planning is carried out before project budgeting and forms the basis for proposing and approving the budget.