You can use the Confirm Repetitive Manufacturing app to carry out the backflush and thus confirm the work progress in repetitive manufacturing.
Note
Link to the Confirm Repetitive Manufacturing app: https://fioriappslibrary.hana.ondemand.com/sap/fix/externalViewer/index.html#/detail/Apps('MFBF')/S34You can also enter confirmations, also called reporting point backflushes, at each reporting point that is set as a milestone.
As a result, according to the settings in the series profile Z001 - report. Point BF/Prel.cost of the Bike Company actual costs are collected on the product cost collector when a reporting point confirmation is carried out as follows:
- The system determines the components by dissolving the current BOM and thus automatically posting the goods issue for the components consumed between two reporting points from the production storage locations.
- An automatic activity allocation is generated.
- Optionally, actual times can be posted if the actual production times differ from the times in the routing.
- Work in process (WIP) and total variances are calculated dynamically and posted in real-time to the product cost collector.
- A total cost posting can be posted at the time of the production cost backflush.
- An automatic goods receipt is posted at the time of the last reporting point backflush.
- At the end of the production process, the system posts the material costs, overhead, and production costs to the product cost collector.
- The system posts single documents for the respective postings and additionally a total document.
- Optionally, the total variance can be split into variance categories by a splitting run.
In repetitive manufacturing, assemblies, components, or operations can be backflushed.