The main control parameters for the execution of an availability check are the Check Instruction and the Check Control. Both parameters will be determined during creation of the demand element (for example, customer order, stock transfer order, …) and via the settings in the material master.

The Check Instruction activates the ATP check and determines the method of the check. Meanwhile, the Check Control defines the elements which should be taken into account during an ATP-check. In addition, the checking group contains the main switch for activating the advanced ATP-check (aATP) in SAP S/4HANA.
Therefore it is necessary to focus in the first step on these two pillars.
Activating and Selecting the Check Method
Once you have decided whether availability has to be checked, you also have to decide which check method to use.