Results of an ATP Check: Availability Control
If the availability check for the order is successful, the system confirms the required material and quantity for the required date. In this case, the user does not notice the availability check. The result is a confirmed schedule line in the sales order. If the availability check is unsuccessful, the system response depends on the Customizing settings. The system can branch to the Availability Control screen or automatically select the delivery proposal specified in the Customizing settings for Availability Check Default Values.
On the Availability Control screen, the system informs the user of the quantities that can be confirmed as required and those that cannot be confirmed as required, and if possible, proposes an alternative delivery.
Note
Fix Quantity/Date: If the customer or order processor accepts the delivery date and quantity proposed and confirmed by the system, this quantity and date can be fixed. The system then transfers the requirement to materials planning so that the confirmed date and quantity can be met. The date and quantity originally required are not forwarded to materials planning. If you do not select the Fix Qty/Date field, the delivery date and confirmed quantity are not fixed. If materials can be either produced or procured more quickly, you may be able to deliver the materials closer to the required delivery date, that is, earlier than the date confirmed by the system. However, the delivery quantity and date may also be negatively affected.
In the Avail. Check Rule field, you can activate or deactivate the Availability Control screen for sales document processing. If the screen is deactivated, the end user cannot manually select a delivery proposal if the availability check is insufficient. Therefore, Customizing settings must be configured to specify how the system is to respond. Is the system to select one-time delivery,complete delivery, or delivery proposal automatically in the background?
If the Availability Control screen is active, you still have to define how the system responds if the availability check is insufficient for functions that run in the background and that check availability (for example, rescheduling).
You can also control whether the Fix Qty/Date parameter on the Availability Control screen is selected by default.