
Suboperations are subordinate to an operation and are hierarchically structured under it.
You can perform the following functions with suboperations:
- Carry out detailed planning for the process step that the operation describes.
- Carry out detailed planning for capacity planning or costing for an operation.
For example, a company uses suboperations at manufacturing centers. You can use suboperations to assign several people or machines (that are required at the same time) to an operation.
- A suboperation can be used with the same work center as the main operation to make a detailed description of every necessary step.
- A suboperation can be used with different work centers as the main operation to operate parallel at different work centers.
- A suboperation can be costed, but you can only schedule it relative to the higher-level operation.
- Cumulate standard values from suboperations in the corresponding operation.
- Determine whether suboperations belonging to an operation are copied to a production order.
Note
Control key
Be aware of the following:
With the control key you are able to define, whether an operation is relevant for scheduling, costing or capacity planning.
The scheduling takes always place at the main operation.
Costing and capacity planning can take place at main operation and / or sub operation side. Therefore you have to define the right control key at main or suboperation level. It is important that you ensure that costs and capacity requirements are not calculated twice.
In the figure Scheduling Suboperations, operation 20 is responsible for ensuring compliance with the production schedule. Suboperations 20/10 to 20/40 are used for detailed capacity planning and costing.
The control key has an important influence on this process when using suboperations.
Scheduling Suboperations

When you specify an offset value, the system determines the start and finish dates of the suboperations.
The reference dates for the start and finish of a suboperation are as follows:
- Start date for setup
- Start date for processing
- Start date for teardown
- Finish date for execution
- Start date for wait time
- Finish date for wait time
If an operation is divided into suboperations, the standard values for the suboperations can be cumulated under the main operation. If the suboperations run in parallel, this kind of accumulation is not possible because the cumulated values will be too high. For example, if you set a start reference for a suboperation to start processing with a time offset of 5- (5 minus) hours, processing (in the suboperation) will start 5 hours before it starts in the main operation.
You can assign an operation which is not to be carried out in the plant (in the operation or routing) to another plant. The plants should belong to the same controlling area. You can assign a suboperation to another plant as its main operation. The unit of measure in the suboperation can differ from the one in the operation.
You cannot assign material components, production resources/tools, or inspection characteristics to suboperations. You can assign them only to operations.