Outlining Make-to-Stock Production

Objective

After completing this lesson, you will be able to get an overview of MTS production

Outline of Make-to-Stock Production

Make-to-Stock Production, For Example, Strategies 10, 40, and 70

In the last lesson, you learned about planning strategy 10. SAP S/4HANA Enterprise Management offers some more plannings strategies for make-to stock production, for example, 40 and 70. These planning strategies provide different approaches to make-to-stock production, allowing companies to choose the one that best suits their business requirements.

The major planning strategies for make-to-stock production are pure make-to-stock production, strategy 10, planning with final assembly, strategy 40, and planning at assembly level, strategy 70.

Characteristics

Make-to-stock production strategies can be executed based on planned independent requirements (PIRs) both on finished product level (for example, strategies 10 and 40) as well as an assembly level, including their final assembly (strategy 70). The PIRs itself are a result of a previous forecast process considering sales order items in previous periods and/or can be created manually. These PIRs represent expected future sales order items – it's a kind of temporary placeholder for them. Depending on the used strategy, sales orders can consume PIRs on header level (strategy 40), on assembly level (strategy 70), or will not affect them (strategy 10).

Make-to-stock production strategies are typically used to ensure a smooth and well-balanced production plan (strategy 10). Deviation on the demand side will be covered by warehouse stock.

Planning Strategy 10: Make-to-Stock Production

With planning strategy 10, sales orders do not directly impact the planning situation. This image illustrates the process of planning strategy 10:

In strategy 10, the sales order doesn't have an impact on production planning. Production of the finished product is triggered by planning only, for example, based on a forecast.

Imagine that the Bike Company plans to produce 50 bikes. This planning is done at the finished product level using PIRs. Now, if a sales order for 10 bikes is received, the PIRs are not immediately consumed. Instead, the 10 bikes are delivered from the existing stock in the warehouse. The reduction of PIRs occurs at the moment of the goods issue.

Application

The Bike Company can choose planning strategy 10 when they have a continuous demand for their bikes. This strategy doesn't automatically start production in case the sales demands are higher than the forecast. In this case, the planner at the Bike Company must manually adjust the forecast.

Planning strategy 10 is one basic strategy for make-to-stock production. Let's take a closer look at how this strategy works:

Planning Strategy 40: Planning with Final Assembly

Planning with final assembly is one of the most common planning strategies in make-to-stock production. It's similar to planning strategy 10 but with a key difference: Sales orders are relevant for planning and can consume planned independent requirements (PIRs):

In strategy 40, planning can be carried out just like in strategy 10, however, sales orders can either consume this planning or even increase the total amount to be produced.

In our scenario, the Bike Company has planned the production of 50 bikes per month. If we receive a sales order for 55 bikes, a shortage of five bikes occurs. In this case, using planning strategy 40, the system automatically triggers the planning of the additional five bikes to eliminate the shortage.

Application

Planning strategy 40 allows you to focus on flexible, automated, and fast reaction to customer demand. This strategy allows for flexibility, automation, and a rapid reaction to customer orders. The Bike Company can apply planning strategy 40 to their assembled bikes, ensuring that they can meet customer demands.

Planning Strategy 40 is one of the most often used planning strategies. Let's take a look how this works:

Watch a Demonstration Video

Watch this video to view a system demonstration how make-to-stock planning with planning strategy 40 works.

Planning Strategy 70: Planning at Assembly Level

With planning strategy 70, the Bike Company can handle the production planning of variants, for example, of bike variants with different bicycle gears.

In this strategy, the Bike Company procures the necessary bike assemblies, excluding the gear variants, without waiting for specific sales orders. When a customer places an order for a particular variant, the final assembly process is carried out using the already stocked assemblies.

Application

Planning strategy 70 is typically used in scenarios where products have configurable or customizable features.

Consumption of Planned Independent Requirements

Consumption of Planned Independent Requirements

You've learned that with planning strategy 40, sales orders can consume planned independent requirements. Next, let’s discover how exactly consumption is performed. The Bike Company can choose between different consumption modes. Watch the following video to learn more about them:

As you have seen in the video, consumption is an interaction between customer requirements and PIRs. In this strategy, PIRs are only seen as placeholders for future sales orders. Using consumption periods, you can limit the consumption. In case a customer demand is lying outside this consumption period, the consumption will not take place.

Summary of Consumption Modes

Consumption mode Consumption mode

The consumption mode determines the direction on the time axis in which the incoming sales orders are to consume the PIR.

Consumption typeConsumption modeExplanation
Backward consumption1The customer requirement consumes planned independent requirements that come before it.
Forward consumption3The customer requirement consumes planned independent requirements that come after it.
Backward and forward consumption2 (or 4)You can combine backward and forward consumption if you take the consumption periods into account.
Periodic-specific consumption5Only planned independent requirements in the related period are consumed.