The Capacity Scheduling Board is a tool to analyze the schedule of operations and to dispatch, reschedule, or deallocate individual bottleneck operations on pacemaker work centers in a graphical chart.

The Capacity Scheduling Board is accessed via the SAP Fiori launchpad. In the app settings, you have to define the area of responsibility and the industry type.
Capacity Scheduling Board: Layout

In the Capacity Scheduling Board, the schedule of operations on work centers is displayed in a graphical chart.
The durations of the operations are displayed as bars on the time axis, taking into account the working and non-working times of the corresponding work centers.
The operations to be evaluated can be selected exactly using filters.
Horizon, work center, work center group and plant behave like regular filters. Work centers that do not meet these criteria are not selected.
All other filters, such as product and status, do not affect the selection of work centers, but they do affect the color of the selected operations.
Operations that match all filter criteria are displayed in green and are referred to as filtered operations. All other operations are displayed in gray and are referred to as unfiltered operations.
In addition to this coloring, the operations are displayed in different color intensities and with additional graphical elements, depending on the order type and the order and operation status.
It is possible to display either the bottleneck operations of pacemaker work centers only, or the operations of all work centers in the defined area of responsibility.
Capacity Scheduling Board: Selecting an Operation to be Rescheduled

In the Capacity Scheduling Board, you can dispatch, reschedule, or deallocate individual bottleneck operations on pacemaker work centers.
To do this, select the operation to be planned, set a suitable planning strategy, and choose the Manage Operation or the Realign Schedules button.
The Manage Operation Chart

After selecting an operation in the Capacity Scheduling Board and choosing the Manage Operation button, the operation to be dispatched, rescheduled or deallocated is displayed in the Manage Operation chart. It is highlighted in green.
In the upper section of the screen, detailed information about this operation and the corresponding order is displayed.
The chart also shows all the alternative work centers or production versions available for dispatching and the time slots available on them.
Manage Operation Chart: Dispatching an Operation

In the Manage Operation chart, select a time slot on the work center to which you want to dispatch the selected operation. Then choose the Dispatch button.
Manage Operation Chart: Dispatching Result

As a result, the operation is dispatched to the selected work center.
Accordingly, choose the Deallocate button to deallocate a selected operation.