The Manage Work Center Capacity app offers you a further option to flexibly evaluate the capacity situation of work center capacities. It is accessed via the SAP Fiori launchpad and provides a user-friendly interface in which the desired information is displayed clearly and concisely, and which can be easily adjusted to individual questions and requirements.

The Manage Work Center Capacity is accessed via the SAP Fiori launchpad.
Manage Work Center Capacity: Overview List and Work Center Details

The overview screen of the Manage Work Center Capacity app displays a list of the selected work center capacities. You obtain aggregated information for the selected evaluation horizon.
Various filters and display options are available. You can display the maximum load, the time of the first overload, the backlog of overdue orders, and the total capacity requirements. The utilization can be displayed graphically in a chart.

Furthermore, you can display the average load, the time of the first critical load, the overall percentage load, and the total available capacity.
The periods of normal load, critical load, and overload are displayed in different colors. The limits for the various load criteria can be set individually.

You can navigate from the overview screen to the display of detailed information on a work center capacity.
You can display the utilization chart in the detail view.

In the detail view, you can also display the pegged requirements, that is, the individual operations and orders. You can use the view settings to display a lot of additional detailed information on the operations.
You can also display and interactively change the shifts of the work center capacity in the detail view.