Browse
/
Learning Journeys
/
Exploring Logistics Projects in SAP S/4HANA
/
Managing Projects with SAP S/4HANA Project System
Evaluating Different Tasks in Logistics Projects
Planning and Execution of Logistics Projects at the Hybrid Machinery Company
10 mins
Describing Typical Activities in Logistics Projects
15 mins
Quiz
Introducing SAP S/4HANA
Managing Projects with SAP S/4HANA Project System
Working with Project Structures
Reporting
Working with Project Plans
Explaining Project Execution
Executing Period-End Closing
Knowledge quiz
It's time to put what you've learned to the test, get 3 right to pass this unit.
1.
Which of the following statements are true?
There are two correct answers.
You can map a project using only one WBS or one network.
You can also represent a project using a WBS and one or more networks.
You cannot use the characteristics of both structures (WBS and networks) together to represent a project.
You can create a project based on an activity.
2.
The individual tasks in the project are mapped as activities in a WBS.
Choose the correct answer.
True
False
3.
Which of the following is used to plan basic dates manually for WBS elements?
There are two correct answers.
Project Builder
Project Planning Board
Easy Cost Planning
Schedule Manager