It’s time to put what you’ve learned to the test, get 8 questions right to pass this unit.
1.
The Project Planning Board helps you to create and edit WBS elements and the project definition.
Choose the correct answer.
2.
The non-stock item category is used for components that are procured via warehouse stock, project stock, or sales order stock.
Choose the correct answer.
3.
Internally processed activities are used for planning work that is to be carried out outside the company.
Choose the correct answer.
4.
When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing.
Choose the correct answer.
5.
What business aspects are managed in project planning?
There are three correct answers.
6.
Which technology is used by the Project Schedule app?
Choose the correct answer.
7.
For which of the following dates can you use scheduling?
There are two correct answers.
8.
The procurement element for external procurement is a planned order.
Choose the correct answer.
9.
Cost planning using activities is the only method used to plan costs for a project in the SAP Project System (PS).
Choose the correct answer.
10.
Using the Project Planning Board, you can select WBS elements and schedule the activities assigned to them.