Controlling Source Determination with Quota Arrangements

Objective

After completing this lesson, you will be able to explain the usage of quota arrangements in source determination

Quota Arrangements Outside MRP

Source Determination with Quota Arrangements Outside MRP

In the source determination process outside MRP, the source with the lowest quota rating is always assigned. If two or more sources have the same quota rating, the system assigns the first item, not the one with the highest quota.

You use the quota base quantity when a new source is included in an already existing quota arrangement, or to remedy a disproportion between quota and quota-allocated quantity.

How to Use Source Determination with a Quota Arrangement Outside MRP

In this demonstration, you will see how to use a quota arrangement while creating a purchase requisition manually for a specific material.

Quota Arrangements in MRP

Prerequisites for Quota Arrangements in MRP

In the planning run, you can split up an individual requirement among various sources. This procedure is called splitting. You control whether a requirement is split or not by using the assigned lot-sizing procedure in the material master record and the minimum split quantity in the quota arrangement header.

In Customizing of the lot-sizing procedure, you can set the indicator for the splitting quota. For example, the Splitting indicator is set for the standard lot-sizing procedure ES (lot-for-lot size calculation with splitting). If you assign this lot-sizing procedure to a material and have a quota arrangement for this material, then each purchase requisition quantity calculated by MRP is split between the various sources of supply for the quota arrangement.

Examples of Using Quota Arrangements in MRP

There is a requirement for 1,000 pieces of material M-01 in whose master record the ES (lot-for-lot size calculation with splitting) lot size has been set. The suppliers currently have the quotas as listed in the following table.

SupplierQuotaQuota-Allocated Quantity
A4420
B3310
C2190
D1100

In requirements planning, four purchase requisitions are generated. The requirement of 1,000 pieces is apportioned among the four sources in the proportion 4:3:2:1. In the case of a quota arrangement with splitting, the quota-allocated quantity and quota rating are both ignored. This results in the following situation after source allocation.

SupplierQuotaQuota-Allocated Quantity
A4820
B3610
C2390
D1200

To prevent the system from splitting up a requirement that is too small, you can specify a minimum quantity for splitting in the quota header. The minimum quantity defines the lowest quantity that a lot must have before it is split up among several sources during the requirements planning run.

Lot Sizes with Splitting Quota

When maintaining a quota arrangement, you can also specify a minimum or maximum lot size for each item of the arrangement. However, the specified lot sizes are only considered in the planning run. The lot size specified in the quota arrangement item overrides the settings in the material master record.

You can define the following lot sizes:

  • Maximum lot size per quota arrangement item

    Maximum lot size is the maximum quantity that is assigned to a source for each procurement proposal in the requirements planning run. If the requirement quantity exceeds the maximum lot size, the quantity is split into several proposal for the same source. To prevent this, you can select the 1x indicator. If you set this indicator, a source is not taken into account for more than one lot with a quantity equal to the maximum lot size. The remaining quantity is then allocated to the remaining sources.

  • Minimum lot size per quota arrangement item

    Minimum lot size is the minimum purchase order quantity that is assigned to a source for a proposal in the requirements planning run. If the requirement quantity is less than the minimum lot size, the minimum lot size for the source is set for the lot.

Example of Maximum Lot Size with 1x Indicator

There is a requirement for 500 pieces of a certain material here it is M-01. The starting situation is as shown in the following table.

VendorQuotaQuota-Allocated QuantityMaximum Lot Size1x
A3100250X
B1200  

You have set the 1x indicator for vendor A. Therefore, a planning run will generate a procurement proposal for 250 pieces with vendor A and a procurement proposal for 250 pieces with vendor B. If you had not set the 1x indicator, the planning run would generate two procurement proposals for 250 pieces with vendor A.

In addition to minimum lot size and maximum lot size, you can also specify a maximum quantity in a quota arrangement item. The maximum quantity is taken into account in both the manual creation of purchase requisitions and the automatic generation of procurement proposals in material requirements planning. The maximum quantity acts as an upper limit for the quota-allocated quantity for a source. A quota arrangement item is not suggested as the source if the quota-allocated quantity is—or would become—greater than or equal to the maximum quantity.

For example, you can enter, as maximum quantity, the target quantity of an outline agreement item that is marked as relevant to MRP in the source list.

Example of Maximum Quantity Without Splitting Quota

There is a requirement for 800 pieces of material M-01.The quota arrangement has been maintained in the system according to the following table.

VendorQuotaQuota-Allocated QuantityMaximum Quantity
A115002000
B23800 

With this starting situation, a planning run would result in the generation of one procurement proposal for 800 pieces with vendor B as the source. Although vendor A has a lower quota rating than vendor B, the maximum quantity would be exceeded because the quota quantity of 1,500 pieces has already been allocated. If the maximum quantity was 2,500 pieces, the system would assign vendor A as the source.

Priority is another option for quota arrangements. For example, you can produce 10,000 pieces of a material per month yourself. Using quota arrangements, you want to procure material that exceeds 10,000 pieces from an external vendor. You achieve this by including the in-house production and the external vendor in the quota arrangement. For the in-house production item, enter a maximum release quantity of 10,000 a month and specify a priority of 1. The item for the external vendor does not require any further indicator.

How to Use a Quota Arrangement in the Planning Run

In this demonstration, you will learn how to use a quota arrangement in the planning run.

Log in to track your progress & complete quizzes