This lesson will guide you through the main steps of managing the processing activities. These are:
- Manage Process Order Batch Details
- Report Processing Start
- Print Finished Product Labels
- Report Processing Completion
- Manage Finished Product Disposition
Manage Processing Activities
Now that the biospecimen shipment has been received and is ready for the processing activities, we can start with managing the process order batch details. For that, you navigate to the Manage Process Order Batch Details application in the Processing Activities section.

Navigate to the process order Batches
From this screen below, we can navigate to the Manage Process Order Batches view of this particular order by clicking on the arrow pointing to the right.

Edit Batch Information for all Subunits
In this view, we have the information on the processing slot (planned start and end date), the associated process order in the ERP, the batches (components and expected yield information), as well as documents and logs. On this screen, we change into the editing mode by clicking on the Edit button on the top right and enter the details-page for each line item in the materials in the process order yield section.

Provide Subunit Batch Data
In this view, we have to provide the information like Batch ID, Subunit Type, Subunit Qualifier and Subunit ID for all associated batches and subunits of the planned processing activities. Save changes by clicking on the Apply button on the bottom right and repeat for all batches and subunits.

Once complete, click on the save button on the bottom right to save all changes and data. With the batch information prepared, the manufacturing organization now can start the processing activities.
Navigate to The Report Processing Start App
For that, select the Report Processing Start application in the Processing Activities section of the SAP Cell and Gene Therapy Orchestration landing page. Select the correct processing activity using the COI ID of the order and clicking on the arrow pointing to the right.

Edit The Processing Start Date And The Date of Formulation
In the next view, we can now switch to the edit mode by clicking on the Edit button on the top right and enter the actual processing start date and the date of formulation in the appropriate fields. This will automatically calculate the expiration date based on your configuration. To save the changes, we click on the Save button on the bottom right.

With the processing steps underway, we need to prepare the finished product labels and also the secondary packaging labels that will be used next. On this same page, scroll down to Process Order Components and click on Add to add the consumed material for this process order (the biospecimen samples that were received from the treatment center). This will open a new window where you can select the biospecimen material that was received.
Add Consumed Biospecimen Material
In the selection window, choose the material that will be consumed by the processing activities (in this case, we will use all cryobags that were received from the treatment center. To save, click on Confirm to save the selection.

With the processing steps now underway, we can prepare the required labels for intermediate and final drug products.
Print Finished Product And Secondary Packaging Label
Using the COI ID, we can navigate to the relevant order and then generate and print all labels that will be needed for the finished product and relevant secondary packaging for the produced subunits.

Report Processing Completion And Yield
With the labels prepared, the next step will be the Report Processing Completion and Yield step which can be found in the Processing Activities section of the SAP Cell and Gene Therapy Orchestration landing page. We can use the COI ID to navigate to the relevant view where we can report on the completion of the processing activities and provide information on the yield for the associated batches. For that, we switch to the edit mode and enter the relevant data for all subunits.

Report Processing Completion And Yield For Subunits
Here, we confirm that the batch subunit has been produced and report on the produced quantity using the appropriate fields and adding the unit of measure. Click on the button Apply on the bottom right to save changes and repeat for all subunits.

Report Actual Processing End Date And Date of Formulation
Once the data has been provided for all subunits, we also enter the actual processing end date and the date of formulation. Now we can save all changes by clicking on the Save button on the bottom right.

Navigate to Manage Product Disposition
Now that the processing steps have been completed and the finished product has been manufactured, we need to manage its disposition. For that, we navigate to the Manage Product Disposition application in the Processing Activities section of the SAP Cell and Gene Therapy Orchestration landing page. Using the COI ID we can navigate to the correct order.

Navigate to Disposition Status of All Batch Items
In the next screen we switch to editing mode by clicking on the Edit button on the top right and then enter all individual batch items that have been produced.

Update The Disposition Status of All Batch Items
Here, we can update the disposition status of all individual items of the produced batches. We can select the correct disposition status and apply changes by clicking on the Apply button on the bottom right. Once this information has been provided for all items, we can save all changes by clicking on the Save button on the bottom right.

This step requires your e-signature. With this, we now have successfully accomplished all processing activities and dispositioned the finished product for being shipped and used at the treatment center.