Overview – Reactive Maintenance (4HH)
This comprehensive nine-step process supports end-to-end maintenance process. First, a maintenance request is created (Initiation). Next, the maintenance request is screened and accepted (Screening). The maintenance request is converted into a maintenance order. During this phase, the required resources for processing the order are also planned (Planning). The maintenance order is then approved for execution (Approval).
Next, the maintenance order is prepared for execution. Various requirements such as stock, non-stock material, purchase requisition, and capacity are reviewed (Preparation). After this, the maintenance order is scheduled for execution (Scheduling). The maintenance order is then executed to repair malfunction (Execution). Then, activities like failure data recording and other post-work activities are carried out (Post Execution). Finally, the maintenance order is reviewed and is technically completed (Completion).
Benefits
- Reduce an asset's downtime and increase productivity
- Enables you to save maintenance costs
Key Process Flow
- Create maintenance request
- Screen maintenance request
- Convert maintenance request into maintenance order
- Plan maintenance order
- Submit maintenance order approval
- Release maintenance order for preparation
- Review maintenance backlog for readiness
- Schedule maintenance orders
- Time confirmation of pre- and main order operations
- Time confirmation of post-maintenance order operations
- Record failure data
- Complete maintenance order technically
Applicable Process Steps


The following tables list the SAP Fiori apps and business roles that are used in the Reactive Maintenance (4HH) process steps:
Process Maintenance Request
Process Step | Business Role | Transaction/App |
---|---|---|
Create Maintenance Request This is Initiation phase of maintenance where an employee can create a maintenance request. | Employee | Request Maintenance (F1511A) |
Review Maintenance Request Employee can check their existing maintenance requests. | Employee | My Maintenance Requests (F4513) |
Screen Maintenance Request This is Screening phase of the process where the supervisor might need to review the maintenance request. Change responsibility of the requests (if required) and take appropriate decision to proceed with request or reject the request. | Maintenance Supervisor | Screen Maintenance Requests (F4605) |
Plan and Prepare Maintenance Order
Process Step | Business Role | Transaction/App |
---|---|---|
Create and Plan Maintenance Order After a maintenance request is approved, we are in Planning phase of this process. The approved Maintenance Request will be called Maintenance Notification. This process step shows how to convert a maintenance notification into a maintenance order and, provides details about planning the resources for the order. | Maintenance Planner | Manage Maintenance Notifications and Orders (F4604) |
Submit Order for Approval After you have planned resources for the maintenance order, it can be submitted for approval to the supervisor. This will set the status of the maintenance order to Ready to Prepare subphase. | Maintenance Planner | Manage Maintenance Notifications and Orders (F4604) |
Approve Maintenance Order (Optional) This process step shows you how to approve a maintenance order from My Inbox (F0862) app. | As per agent determined in the workflow. | My Inbox (F0862) |
Review and Release Maintenance Order We are in Ready to Prepare subphase. In this process step, you can review a list of approved maintenance orders and release them for Preparation phase. | Maintenance Planner | Manage Maintenance Notifications and Orders (F4604) |
Maintenance Backlog Overview The maintenance order is in Preparation phase now. Maintenance Backlog Overview screen will allow you to view various cards. You can check Maintenance Backlog Card which shows backlog of maintenance orders based on phase or buckets. | Maintenance Planner | Maintenance Backlog Overview (F5105) |
Manage Components and Services With this app, you can view and manage all externally-procured materials and lean services that are required to execute your maintenance orders in a single place. | Maintenance Planner | Manage Components and Services (F6178) |
Convert Purchase Requisitions to Purchase Orders This process step shows you how to assign purchase requisitions to a source of supply and to convert assigned source purchase requisitions to purchase orders. | Purchaser | Manage Purchase Requisitions (F1048) |
Goods Receipt for Purchase Order Here you post the goods receipt for the purchase order. | Warehouse Clerk | Post Goods Receipt for Purchasing Document (F0843) |
Post Goods Issue You are now in Execution phase of the process. Here you post the goods issue from storage location. | Warehouse Clerk | Post Goods Movement (MIGO) |
Submit Order for Scheduling Once Preparation is done and backlog is reviewed, the order can be set for Ready to Schedule to start Scheduling phase. | Maintenance Planner | Find Maintenance Order (F2175) |
Schedule Maintenance Order and Submit it for Execution In this step, you can schedule the order operations and set the operations ready for execution. | Maintenance Planner | Find Maintenance Order (F2175) |
Execute Maintenance Order
Process Step | Business Role | Transaction/App |
---|---|---|
Execute Maintenance Order In Execution phase, technician will execute pre and main operations. | Maintenance Technician | Perform Maintenance Jobs (F5104A) |
Main Work Completed After execution of Pre and Main work by the Technician, the Maintenance Supervisor will review the work and change the status from Main Work Completed to Post Execution phase. | Maintenance Supervisor | Find Maintenance Order (F2175) |
Maintain Service Entry Sheet In this activity, you report the performed services in the service entry sheet. | Purchaser | Manage Service Entry Sheets - Lean Services (F2027) |
Execute Post Work Operations In this process step the technician will execute post operations activities (if any) and also update the malfunction details and failure data. | Maintenance Technician | Perform Maintenance Jobs (F5104A) |
Review Failure Data In this step, the supervisor can review the failure data updated by the technician. | Maintenance Supervisor | Find Maintenance Order (F2175) |
Review Maintenance Cost Maintenance planner can review the cost of maintenance orders. | Maintenance Planner | Maintenance Order Costs (F4603) |
Technically Complete Maintenance Order The maintenance notification is completed and the maintenance order is technically completed after the required maintenance work has been performed. The technical completion reduces all the purchase requisitions, open reservations, and capacities still outstanding for the maintenance order. Nevertheless, the order can continue to receive costs, for example, through invoice receipts for delivered and used materials. However it is blocked for all changes in the processing. The order settlement transfers the costs incurred that were temporarily collected for the maintenance order, to the recipient, for example, to the cost center for the maintained object. This process step shows you how to technically complete a maintenance order. | Maintenance Planner | Find Maintenance Order (F2175) |
Create Supplier Invoice with PO/GR Relation In this process step you create the invoice with reference to the purchase order. | Accounts Payable Accountant | Create Supplier Invoice - Advanced (MIRO) |
Release Supplier Invoice In this process step you release a blocked supplier invoice. | Accounts Payable Accountant | Supplier Invoices List (Version 2) (F1060A) |
Additional Features – Reactive Maintenance (4HH)

With this app, you can view and manage all externally-procured materials and lean services that are required to execute your maintenance orders in a single place.
You access this app by choosing the procurement activity Create Purchase Requisition on the External Procurement card in the Maintenance Backlog Overview. By default, the system displays all non-stock components and lean services in the selected maintenance planning buckets for which a purchase requisition needs to be created
Value Proposition: Improved visibility of components & services performed by external service providers
Capabilities
- Filter externally-procured components and services by one or more maintenance planning buckets, pending procurement activities, and other criteria
- The system displays all non-stock components and lean services that match the selected filter criteria
- Navigate to the maintenance order to which a non-stock component or lean service is assigned
- From the maintenance order you can, for example, create a purchase requisition for the relevant non-stock component or lean service
- View the order operation to which a non-stock component or lean service is assigned, and navigate to the object page to view the operation details