Processing Budget Releases

Objectives

After completing this lesson, you will be able to:
  • Use budget releases
  • Handle different time spans between budget planning and execution

Overview: Budget Releases

Budget Releases

Budget releases are a mechanism for handling different time spans between budget planning and execution. This means that while a budget might be planned for a complete year, it will not be consumed on the first day of this year. Instead, the budget will be released, and made available for consumption and AVC checking over time.

Budget releasing can be processed using an individual manual budget posting or through an automated mass process (or a mixture of both for a different context).

Unreleased and released budget is modeled using different budget types. Budget releases are simply specific budget transfer documents between these budget types. Of course the unreleased and released budget can be combined or separately reported in analytics.

The functionality of budget releases is not switched on or off. In fact, you can enter budget directly into unreleased and released budget at the same time. Of course if all your budget will be subsequently released, you would never enter budget directly into released budget, but always use the release functionality for all your budget.

The following figure shows the process of budget releases.

Flowchart representing the process of budget releases beginning with entry of a budget and remaining in a not available for consumption state. When the budget document is released it becomes available for consumption.

Budget Type Configuration

The following figure shows the configuration of the Budget Type for unreleased and released budget. The released budget type is consumable, whereas the unreleased budget type is not.

UI example of a Define Budget Type: Change page displaying released and unreleased budgets.

Manual Budget Releases

The following figure provides you with the example of a budget release document. You can create those documents manually or using a period job.

To create a document manually, you need to choose the budget process "Release" in the Maintain Budget Document app. The app will propose immediately a transfer document. When you enter a sender line, the system will generate a corresponding receiver line.

It is possible to change the account assignment on the receiver side (or create multiple line items to different account assignments). The budget types are controlled along the release concept. You cannot release more budget than is available under the unreleased budget type.

UI example of a Budget Document page defaulted to the General Information tab displaying budget sender items.

Automatic Budget Releases

Frequently, a budget release will be posted periodically using an automated process. You can trigger this type of periodic release using the Application Jobs app. To do this, select the job template, Automatic Budget Release. You can start this job for all or individually selected account assignments.

The automatic budget release generates budget release documents in line with the manual creation of budget releases.

The following figure shows the parameters for an automated budget release job.

UI example of a New Job: Automatic Budget release page displaying the parameters for an automated budget release job with budget types for sender and receiver information.

Partial Budget Releases and Recurrence Patterns

Partial Budget Releases

If you choose not to release the complete amount immediately, it is possible to choose a period for which you can release portions of your unreleased budget. This is achieved using the recurrence pattern in the job. The following figure, Define Recurrence Patterns, provides you with the example of an unreleased budget that will be released each month for 12 months. In this case, the system automatically divides the unreleased budget by the number of remaining periods.

It also reacts to new supplements or returns that might change the remaining unreleased budget. In other words, the system will release the complete budget over the scheduled period (even if the budget amount on the specific accounts assignments changes during the completed period).

Note

As the system calculates the outstanding remaining periods, you should always choose a defined end in the recurrence pattern of your job.

UI example of the Scheduling Information window that allows you to define recurrent patterns according to the preceding text.

Partial Release with Changes in the Overall Release Period

Release job is set up for 10 periods.

Example: Partial Release with Changes in the Overall Release Period

ActionUnreleased BudgetRemaining Periods before Job startBudget to be released
Job run for Period 1$100010100 (1000/10)
Job run for Period 2$9009100 (1000/9)
Job run for Period 3$8008100 (1000/8)
Supplement of $49$7497-
Job run for Period 4$7497107 (749/7)
Job run for Period 5$6426107 (642/7)
Job run for Period 6$5355107 (635/7)
Return of $28$4285-
Job run for Period 7$4004100 (400/4)
Job run for Period 8$3003100 (300/3)
Job run for Period 9$2002100 (200/2)
Job run for Period 10$1001100 (100/1)
It is also possible to create an extensibility through custom logic in order to calcluate different release values based on external factors. The extension point is called PSM_BUDGET_MAINTAIN_BADI (Calcuate Budget Release Amount).

Summary

You should be now able to understand the process of releasing budget.

The key takeaways are as follows:

  • Budgets can be released using manual or automatic postings
  • Unreleased and released budgets are modeled using different budget types
  • Partial release are achieved using the recurrence pattern in the job parameters

Release Budget

Watch the simulation Release Budget to learn more about the system-related activities.