Maintaining Full Settlement of Investment WBS Elements

Objective

After completing this lesson, you will be able to explain the partial capitalization and full settlement of an investment WBS element

Settlement Rules

The welding cell has now been completed and is to be used in the Bike Company. The welding cell consists of more than one fixed asset. Kevin needs to create new fixed assets, such as welding table and welding cell.

The figure illustrates the process of settlement. It starts with initial financial activities such as down payments, special depreciation, and acquisitions. These are managed by settlement in the Assets under Construction. After completion of the construction phase, the assets are either partially capitalized or fully settlement, resulting in completed assets.

The settlement rule must settle 100% in total. This means that 100% of the asset under construction is credited for a full settlement (settlement type FUL).

CategorySettlement Receiver%Settlement Type
FXA20000160FUL
FXA20000240FUL
 Sum100 

Full settlement is performed using the same Run Settlement - Actual app as periodic settlement. The difference lies in the processing type.

Two processing types are possible: Partial Capitalization or Full Settlement.

Full settlement takes place when the investment project is completed. With the full settlement, the debits that were transferred to the asset under construction are settled to completed assets.

If debits were transferred incorrectly to the asset under construction, you can make a correction at this point and make a final settlement of these debits to cost centers. However, this is allowed only for debits that were posted during the current fiscal year. Debits from previous fiscal years cannot be settled to cost centers at this point because they were already listed under assets under construction in the balance sheet from the previous year.

CategorySettlement Receiver%Settlement Type
FXA20000190FUL
CTR1010110110FUL
 Sum100 

Note that you can still post acquisitions to the investment project after the full settlement. There is no change to the status of the investment projects. Therefore, you can have any number of full settlements for the same investment project

Maintain the Settlement Rule

Watch the video to learn how to create a settlement rule for full settlement.

Let's help Kevin maintain the settlement rule.

Processing Options

We can use the following processing types for full settlement:

  • Partial Capitalization

    Before carrying out the full settlement, the system automatically carries out a periodic settlement. This procedure ensures that all of the debits posted to the investment that require capitalization have been settled to an asset under construction.

    The system settles all debits that have been settled to assets under construction. They are settled to the final receiver assets, which have been assigned a full settlement rule.

  • Full Settlement

    The system not only settles the costs in the period, it also determines the cumulative balance on the order up to the settlement period. If there is a outstanding balance, the system issues an error message.

The figure shows the process of periodic settlement and full settlement for an investment project. It starts with the investment project being divided into three work breakdown structure (WBS) elements, each of which has an investment profile. WBS element 1 settles 100 to an asset under construction (AuC 1), which is then fully settled to asset 1 (40%) and asset 2 (60%). WBS element 2 settles10% to a cost center and 90% to an asset under construction (AuC 2), which is then fully settled to asset 3 (100%).WBS element 3 settles 100% to AuC 3, which is then fully settled to cost center (10%) and asset 4 (90%).

Kevin's Key Takeaways

Note

  • Create Assets
  • Maintain settlement rule with settlement category FUL
  • Sum must equal 100%
  • Execute settlement per ledger

Perform Full Settlement and Analyze the Result

Watch the video to learn how to create a settlement rule for full settlement.

After Kevin has maintained the settlement rule, he needs help to start a full settlement run for the welding cell.

Log in to track your progress & complete quizzes