Knowledge quiz

It’s time to put what you’ve learned to the test, get 3 questions right to pass this unit.

1.

Select the possible sources of supply that can be used by an MRP run for an externally procured material.

There are three correct answers.
2.

For what purpose can you use source lists for source determination during the planning run?

There are two correct answers.
3.

What elements can be generated as a result of a planning run for externally procured materials? 

There are two correct answers.
4.

Using a quota arrangement, MRP can split and distribute the needed quantity over multiple sources of supply.

Choose the correct answer.