As a project manager, you want employees to document their tasks by confirming their working hours and dates. This information provides you with an overview of how the project is progressing, and enables you to identify any inconsistencies early on. For this reason, you require the following knowledge:
- An understanding of how to confirm tasks
- An understanding of how to confirm tasks with the Cross-Application Time Sheet (CATS)
- An understanding of how to confirm checklist items
Task Confirmation
You can use confirmations to document the processing status of project elements and enter the current data for project elements. In Project Management, you can confirm tasks and checklist items. However, you can only enter confirmations if the task or the checklist item has the status Released or In Process.
You can enter the actual start, actual work, actual finish, percentage of completion, and status. You can open tasks, notes, and documents. You can copy planned dates to actual dates.
You can confirm the following data for each task:
- Actual work
- Actual start date
- Actual finish date
- Remaining work
- Percentage of completion
There are also alternatives for confirming tasks:
- You can enter the actual data directly in the detail screen of a task
- You can use the tabular view displayed in the figure
- You can use the CATS integration
To enter the confirmation data directly in the tasks detail screen, choose the Dates and Work tab page. On this tab page, you can enter working hours and the percentage of completion. The remaining work is the difference between the planned work and the actual work. If you select the Remaining work manually checkbox, the system does not calculate the remaining work, and you can enter it directly.
The percentage of completion is independent of the planned work, actual work, or remaining work. Besides work, you also specify the actual start date and the actual finish date.
When you execute a task, you can also set the In Process status. This indicates that the task has begun but has not been finished. The In Processing status is set in addition to the Released status. When the task is completed, you can set the Closed status. When the Closed status is set, you can no longer change the confirmed data, however, you can reset the status. The Canceled status is used when a task is terminated. If this status is set as Canceled, you can no longer change the task, and any relationships to other tasks are deleted.
The figure shows the confirmation of tasks in a tabular view. The advantage of this view is that you can confirm tasks for multiple projects together. You can confirm actual dates and working hours, add documents, and copy planned dates to actual dates.
Hint
As an alternative to time recording of tasks, you can also post working hours relating to project roles. To do this, the project type must be configured accordingly. An additional checkbox controls whether you can enter additional time for the project definition.
Task Confirmation with CATS (Cross-Application Time Sheet)
You can use CATS to enter the working time for tasks or project roles from SAP Project Management. If prerequisites are applied, the worklist in the time sheet is filled with the tasks and roles that are assigned to a user or the users for which they are responsible.
Tasks and roles are selected from the worklist and their respective working time is entered. These working times are transferred to SAP Project Management and are available for reporting. These working times are also updated in the account assignment objects in accounting integration. This means the actual costs are updated in the internal order or on the work breakdown structure (WBS) element that is assigned to the project element.
The preceding figure provides you with an overview of the individual steps for time recording using the time sheet.
Hint
You must use a worklist in CATS to enter times for SAP Project Management. You can only enter times for project elements that are contained in the worklist.
Time Recording with CATS2
The following prerequisites must apply to enable time data entry on the time sheet:
- In SAP Project Management, the project type must allow time recording with CATS.
- Accounting integration must be active for the project.
- You must have performed resource planning and staffing for the projects.
- A personnel number must be assigned to the business partner.
- If the Project Management system and the system for CATS are not identical, you must set up an Application Link Enabling (ALE) connection between both systems.
- A suitable data entry profile must be set for the time sheet.
- If you want to edit detail information (such as remaining work), in the transaction CAT2, you have to activate the CA_CATS_CPR_CORE business function in the Switch Framework (transaction code SFW5). This business function is shipped with enhancement package 3 for SAP ERP.
Hint
SAP Note 954860 describes how you can set up the ALE connection.
SAP Note 913347 describes a scenario where SAP Project Management and CATS are installed on the same system.
The entered times and the associated costs are transferred to accounting using the transaction CATA. For SAP Project Management, you transfer the data manually by using the DPR_CATS_CPR_TRANSF report. During the transfer, the actual start date is also transferred. The earliest actual start date is saved on the project element. The confirmation entered in CATS does not change the status of the project element.
CATS are also available in a web based user interface. This improves usability and provides a unique and seamless interface. In this case, a worklist can also be used to identify possible objects to record times. Furthermore, a calender is provided to support users with already recorded times, as well as working days.