Using the Phase Model
Using the Phase Model
Describing Benefits
15 min
Initiation and Screening
30 min
Planning, Approval and Preparation
30 min
Scheduling, Execution and Completion
20 min
Customizing the Phase-Based Process
30 min
Quiz
Managing Inspection Checklists
Managing Inspection Checklists
30 min
Customizing Checklists
30 min
Quiz
Using the Phase Model
Describing Benefits
15 min
Initiation and Screening
30 min
Planning, Approval and Preparation
30 min
Scheduling, Execution and Completion
20 min
Customizing the Phase-Based Process
30 min
Quiz
Managing Inspection Checklists
Managing Inspection Checklists
30 min
Customizing Checklists
30 min
Quiz
Knowledge quiz
It's time to put what you've learned to the test, get 6 right to pass this unit.
1.
Status Main Work Completed indicates that ...
Choose the correct answer.
… the order has been technically completed.
… the order has been finally confirmed.
… the order operations with execution stage Main are complete.
2.
Resource Scheduling (RSH) is mandatory for scheduling of phase-based orders.
Choose the correct answer.
True
False
3.
The Overall Status Profile MAINTJOB is used ...
Choose the correct answer.
… only for notification type Y1.
… only for app Report and Repair Malfunction.
… only for order type YA01.
4.
Which statements about Event Prioritization are correct?
There are two correct answers.
… enables you to assess priorities based on consequence categories, consequences, and likelihoods.
… is a setting of the order type.
… can be activated for both notifications and orders.
… calculates and suggests the applicable priority for the maintenance request.
5.
A planning bucket ...
There are two correct answers.
… is created during the preparation phase and supports you managing your maintenance backlog.
… is a pool of notifications, which is automatically converted into orders.
… is a selection of order operations for the time confirmation.
… can be used for recurring work.
6.
The phase model ...
Choose the correct answer.
… replaces the standard process Corrective Maintenance.
…only runs with Reactive Maintenance (4HH).
… is based on Best Practices and provides nine phases.
7.
What can you do during Screening of a maintenance request?
There are two correct answers.
Create a maintenance order.
Accept the request.
Set request to Action Required.