Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

The total quantity of all relevant assigned planned orders for a material goes into the quota-allocated quantity. If the planned order is converted to a requisition, the quota-allocated quantity is updated once more. True or false?

Choose the correct answer.
2.

The lot size specified in the quota arrangement item overrides the settings in the material master record for the planning run. True or false?

Choose the correct answer.
3.

Which of the following is used for manual control of the quota arrangement when new sources are included?

Choose the correct answer.
4.

For transactions outside the planning run, what flow logic does the system use for source determination?

Choose the correct answer.
5.

Which of the following statements are true when creating source list records for a material?

There are two correct answers.
6.

By blocking a source list entry with outline agreement item, you can still order the material without reference to the outline agreement item from the same supplier. True or false?

Choose the correct answer.
7.

You can use the source list to prevent materials from being ordered with reference to a material group contract item. True or false?

Choose the correct answer.
8.

You can enter only suppliers and plants in the quota arrangement, but no outline agreement items. True or false?

Choose the correct answer.
9.

In automatic source determination, the system can find sources for an item without a material master record even if the material group of the outline agreement item or info record is different from the material group of the requested material. True or false?

Choose the correct answer.
10.

You should use the regular supplier if you only have info records for a material and if you prefer not to create a source list to control sourcing. True or false?

Choose the correct answer.