Setting Up Part-Time Work Schedules

Objective

After completing this lesson, you will be able to set up a part-time work schedule

Part-Time Working Provisions

You can set up part-time working provisions in two different ways. You can either create your own work schedule rules for your part-time employees or modify the work schedule rules that exist for your full-time employees.

Separate Work Schedule Rules

To create a separate work schedule rule for part-time employees, follow the same procedure as you did for creating work schedule rules for your full-time employees. A work schedule rule for your part-time staff can be used for all employees who are to work according to this rule.

To create separate work schedules, you perform the following steps:

  1. Set up elements, such as daily work schedules, period work schedules, and work schedule rules, and so on, in Customizing
  2. Generate a work schedule from the elements
  3. Assign the work schedules to part-time employees in the Planned Working Time infotype (0007)

Part-Time Work Schedules

If your company employs part-time employees in addition to full-time employees, you can create separate work schedule rules for your part-time employees.

The following table lists the work schedule rule that needs to be created for each type of working option:

Part-Time Working OptionWork Schedule Rule
Fewer working hours every dayYou need to define the shortened working time in the daily work schedule by specifying fewer planned working hours, for example 4 instead of 8.
Fewer days in a week, but the same daily work schedules as full-time employeesYou can group the daily work schedules into an applicable period work schedule. For example, you can make it a 3-day working week instead of 5.
Fewer working hours each day and fewer days each weekYou need to define the shortened working time in the daily work schedule and group the daily work schedules into an applicable period work schedule.

Modification of an Existing Work Schedule

To specify a part-time rule based on a full-time work schedule rule, you need to modify the average working hours in the existing daily work schedule in the Planned Working Time infotype (0007). This has to be done for each applicable employee.

Modifying the existing work schedule involves setting the employment percentage, the working hours per day, week, month, or year, to a lower value. You can use the function for creating daily work schedules dynamically to specify variable working times for part-time employees in your enterprise.

Modification of Infotype 0007

To specify a part-time rule based on a full-time work schedule rule, you must change the average working hours of the full-time work schedule rule in the Planned Working Time infotype (0007) for each employee individually. This can be done in one of the fields in the Working time section of the Planned Working Time infotype.

The fields that you can overwrite are Employment percent,Daily working hours, Weekly working hours,Monthly working hours, and Annual working hours. If you overwrite one field, the other fields are automatically adjusted. As soon as the employment percentage is less than 100%, the Part-time employee field is activated. In addition, the personal work schedule for the employee is modified accordingly to reflect the part-time working hours.

Note

You can customize which of the hours fields are ready for input. In the standard system, only the Daily working hours field is active.

Part-time work can also be specified in the Planned Working Time infotype (0007) using the Dynamic daily work schedule function. In this way, you can overwrite specific fields of the daily work schedule for part-time employees according to the specifications in the Planned Working Time infotype (0007).

Leave Modification

If quota entitlements, such as leave, need to be reduced for part-time employees, you need to create the required reduction rules with the necessary conditions in Customizing.

You can modify the leave entitlement according to the employment percentage for your part-time employees in the Planned Working Time infotype (0007). Alternatively, you can modify the capacity utilization level in the Basic Pay infotype (0008) or the Weekly workdays field in the Planned Working Time infotype 0007.

Set Up a Part-Time Work Schedule

Business Example

Some employees at your enterprise work part-time. As a part of your job, you need to set up the part-time work schedule for many of these part-time employees. For this reason, you need to know how to set up part-time work schedules by modifying the existing work schedule rule.

Set up a part-time work schedule for your hourly wage earner whose personnel number is 306991## (## = your group number).

Steps

  1. Set the part-time employment percentage to 50% for your hourly wage earner starting on the first of the month after next.

    1. On the SAP Easy Access screen, choose Human ResourcesTime ManagementAdministrationTime DataMaintain.

    2. In the Personnel no. field, enter the personnel number of your hourly-wage earner 306991##.

    3. On the Time management data tab page, choose the Planned Working Time infotype.

    4. Choose the Copy pushbutton.

    5. On the Copy Planned Working Time screen, enter the first day of the month after next as the start date.

    6. In the Employment percent field, enter 50 and press ENTER. Choose Enter to confirm the subsequent warnings. The Part-time employee and the Dyn. daily work schedule options are automatically set.

    7. Check how the employee’s working times have changed.

    8. Save your data. Choose Enter to confirm the system warning. Choose Save.

    9. If prompted to create a home work center, choose the Cancel pushbutton.

    10. Return to the SAP Easy Access screen.