Planning
The Planning phase begins when a maintenance request is accepted. The accepted maintenance request is now known as a maintenance notification. As a Maintenance Planner, you can now create and plan orders.
In the Manage Maintenance Notifications and Orders app, maintenance orders can be created for one or more maintenance notifications. Alternatively, you can assign an existing maintenance order to a maintenance notification. Information from the leading maintenance notification is copied into the maintenance order. The quick view for maintenance order allows you to navigate to related apps. Orders can also be created in the Create Maintenance Order app.
In the Change Maintenance Order app, you can add information related to operation, material, labor, services, and cost to plan the order. Only as a Maintenance Gatekeeper, you can change the final due date and priority for the maintenance order.
When you create an order, the order is in the Planning phase and sub-phase In Planning (Order). Depending upon the configuration of the order type in the SSCUI Activate Workflow for Order Type, an order needs a cost approval. An order can be released without an approval if the order type is not configured for workflow. If the workflow is configured for the order type, the order goes through the workflow steps for approval. If the workflow is configured for automatic approval, then the order is approved immediately. If workflow is set up for manual approval, it will move to the approver's inbox.
You can submit an order for approval from Manage Maintenance Notifications and Orders app and Change Maintenance Order app.
As a maintenance planner, you need to ensure that a maintenance order has all the operations, required components, resources, and documents to perform the maintenance. The system will calculate the planned costs for the maintenance.
If the maintenance order type is configured for cost approval, then the planner will submit the order for cost approval.
The submitted order moves to My Inbox app. When an order is submitted for approval, the phase and sub-phase of the order are Approval and Submitted for Approval (Order) respectively. If the order is approved, then the sub-phase of the order is Approved (Order). If the order is rejected, then the sub-phase is Rejected (Order).
You can release the accepted maintenance orders for preparation. You can edit a rejected maintenance order and submit it for approval. It then moves to the Approval phase.
The SAP Fiori apps applicable for this phase are:
Manage Maintenance Notifications and Orders (F4604)
Manage Maintenance Notifications and Orders (F4604)

With this app, you can manage maintenance notifications and maintenance orders. You can create orders for maintenance notifications and assign existing orders to notifications. Each order has a header notification. The notification from which an order is created becomes its header notification and inherits its data.
This app is available with the role SAP_BR_MAINTENANCE_PLANNER. You can:
Get a combined view of Maintenance Notifications and Maintenance Orders
Create maintenance order for maintenance notifications
Assign maintenance notifications to existing maintenance order
Mass change capabilities for maintenance notifications and orders
Submit work orders for approval
Release work orders for preparation
Unassign maintenance notifications from work orders
Note
By default only Maintenance Notifications of type Y1 (Reactive Work) are displayed. In this app, you can only view notifications of new scope items (4HH, 4HI, 4VT, 4WM). This app does not display notifications of old scope item (BH1, BH2 and BJ2)
Key Features
- View maintenance notifications that are screened and accepted.
A maintenance request is created for a technical object.
The new maintenance request is available for screening and acceptance.
The screened maintenance request is available in this app for processing.
Filter maintenance notifications. By default, the system displays reactive maintenance notifications (notifications of type Y1) with a date range of +/- 15 days. You can clear the default parameters to view the complete list of notifications and orders.
Group and sort maintenance notifications or maintenance orders.
View details of a maintenance notification such as priority, failure mode, final due date, associated orders, and so on.
View details of a maintenance order such as priority, failure mode, final due date, associated notifications, and so on. Orders that are in status Closed (CLSD) are not displayed here.
Create a maintenance order for a single maintenance notification. Select a maintenance notification and create a maintenance order. When you create an order for a notification, the notification becomes the leading notification for the order. The order inherits details from the notification. The new maintenance order has a unique order number. You can create an order for a notification only if the notification is not already assigned to an order.
Create a maintenance order for multiple maintenance notifications. Select multiple maintenance notifications and create a maintenance order. If a maintenance order is created for multiple maintenance notifications, the leading notification is displayed. To view other notifications associated with the maintenance order, choose More.
You can create multiple orders for multiple notifications. For each of the notifications you selected, a separate order will be created.
You can create a single order for multiple notifications. For all the notifications you selected, a single order will be created and you can assign one of the notifications as the leading notification.
You can assign a single order to multiple notifications. If you receive a notification for the same object and if the problem is the same, then you do not have to create a new order. You can assign the existing order that has already been created for the problem to the notification.
You can unassign orders from a notification but, you cannot unassign orders from a leading notification. To switch the leading notification,navigate to the Change Maintenance Order app. Enter the order number and navigate to the Detail page. In the Object List tab, remove the flag for Header Notification.
Some orders require an approval based on order attributes and cost. You can configure workflow rules to determine the approvers for the order. For orders that require approval, the planner has to request for approval.
- Submit, approve, or reject an order.
The submitted order is available in My Inbox app where you can approve or reject the order.
Once an order is approved, it can be released.
You can submit a rejected order for approval.
Change responsibility for the maintenance notification and maintenance order. For each attribute, you can keep existing values, select new values, or leave the field blank. You cannot update orders if order has been submitted for approval.
Release accepted orders for preparation of materials and services required for the order.
Navigate to related apps from the object page.