The actual goods receipt posting can be triggered in different ways, but for a decentral environment it is always done in EWM.
Explicit Goods Receipt Posting
Explicit goods receipt posting means that you start with the goods receipt posting as first activity in the warehouse. There are various possibilities to do this:
- Goods Receipt + Save in the inbound delivery:
You can use the transaction or app for the processing of the inbound delivery to trigger the goods receipt.
- Physical Goods Receipt:
This transaction offers possibilities to search for the inbound delivery through all kinds of information, like purchase order or door. You can process each individual item, like change quantities, pack, add information like serial number or batches and mark the item for goods receipt.
- When using the yard, you can post the goods receipt for the complete transportation unit content when it has arrived in the yard.
A transportation unit is for example a truck. The content is the associated inbound deliveries.
The posting of the goods receipt can of course trigger the creation of the warehouse tasks for putaway.
Note
The automatic creation of the warehouse task in the event of a explicit goods receipt posting does not happen in our system, as we often create warehouse tasks in the foreground to control strategy settings.
Implicit Goods Receipt Posting
Instead of posting the goods receipt as first step in warehouse processing, you can simply create the warehouse task. The confirmation of this warehouse task will automatically trigger the goods receipt posting in EWM and in ERP. But there are some things to consider:
- Confirmation of the warehouse task in a complex scenario: A complex scenario would be, for example, if there is first a task for unloading, then a warehouse task for a movement to a packaging work center, finally a warehouse task for putaway in the destination bin. The goods receipt posting is done with the confirmation of the first warehouse task, so with the unloading step. In case of an ROD/AFS scenario (described in the next lesson) the system would trigger a posting change once the material arrives at the final bin.
- When confirming warehouse tasks with mobile devices, the user confirms task by task. If, for example, the inbound delivery contains several items or HUs, and each of them is an individual warehouse task, each time such a task is confirmed the goods receipt for the warehouse task content is posted. That leads to a bigger quantity of material documents in the ERP system, especially if that is then again combined with the ROD/AFS scenario (which then eventually doubles the number of material documents).
You can influence that the goods receipt posting is sent back to ERP only when the GR is completely done in EWM or when the putaway is completed. However, this means that during this time a stock difference between ERP and EWM exists (the GR posting in EWM is definitely done, this can not be avoided or delayed). The Goods Receipt Mode can be set in the Control Parameters for ERP Version Control or in the Process Profile for the inbound delivery. The process profile option is available because the control parameters for ERP version control option does not exist in embedded EWM.
Note
With SAP S/4HANA 1909 there is a new option in the document type for inbound deliveries that the creation of the warehouse task is not allowed before the goods receipt posting.
Synchronous Goods Receipt In Embedded EWM
In SAP S/4HANA with embedded EWM, it is possible since release 2020 FPS01 to work without inbound deliveries for external procurements. The goods receipt posting on the ERP side creates a synchronous goods receipt posting in EWM and can create the warehouse tasks for putaway automatically.