Introduction to MRP
The procurement process can be simplified by automating individual steps. This begins with the determination of requirements. You can create purchase requisitions automatically using the Material Requirements Planning (MRP) instead of entering them manually in the system. This requires specific configuration activities and the maintenance of MRP relevant material master data.
Hint
SAP S/4HANA offers two options for carrying out material requirements planning: In addition to the classic MRP run, SAP S/4HANA also offers a new MRP run optimized for SAP HANA: MRP Live.
The central function of material planning is to ensure material availability, that is, the timely procurement of the required requirement quantities for production and sales. MRP is used to monitor stock levels, identify shortages, and automatically generate procurement proposals for purchasing and production.
Possible procurement elements in MRP are planned orders, purchase requisitions, and delivery schedule lines.
For materials produced in-house, the system creates planned orders to plan the production quantities. Once planning is complete, the planned orders can be converted into production orders.
For externally procured materials, you must distinguish between MRP Live and classic MRP:
MRP live always creates delivery schedule lines for externally procured material with valid scheduling agreement and it creates purchase requisitions for all other externally procured material.
With classic MRP, you decide whether the system creates a planned order or directly a purchase requisition for planning the externally procured quantity. Planned orders and purchase requisitions are internal planning elements that can be changed, rescheduled, or deleted at almost any time. When a planned order is created, a buyer can only order the material after the MRP controller has checked the planned order and converted it into a purchase requisition. A purchase requisition is immediately available to Purchasing.
If a scheduling agreement exists for a material, it is also possible to generate delivery schedule lines directly in the classic requirements planning run. In contrast to planned orders and purchase requisitions, delivery schedule lines are fixed elements with a binding character.

Planning Level and Prerequisites
The organizational level relevant for MRP is the MRP area. MRP areas can only be defined within a plant, not across plants. Basically there are three types of MRP area:
Plant: The system automatically creates a plant MRP area for each plant. The number of a plant MRP area corresponds to the plant numbers. If no other MRP areas exist, the plant MRP area covers the entire plant. If you carry out MRP at plant level, you do not need any further configuration.
Storage location: MRP areas for storage locations consist of one or more storage locations within a plant. If you want to plan storage locations separately within a plant, you must configure the MRP areas according to your requirements.
Subcontractor: Subcontracting MRP areas are used to plan the provision requirement for a subcontractor separately and are defined by the assignment of this subcontractor.
Note
In SAP ECC, you need to activate the MRP areas in Customizing. Accordingly, you can work in SAP ECC with or without MRP areas. If you have not activated MRP areas in SAP ECC, you run MRP at plant level (even a simple form of separate MRP for storage locations is also possible in SAP ECC).
In SAP S/4HANA, the MRP area is active by default and cannot be deactivated. The MRP area is therefore the only planning level in SAP S/4HANA.



