Testing Configured Business Processes

Explaining the Test Strategy

Objective

After completing this lesson, you will be able to explain the types of tests and overall test strategy

Test Strategy Overview

Implementation projects use three types of testing, each serving a distinct purpose:

  • Implementation testing
  • User acceptance testing (UAT)
  • Regression testing
Graphic mapping the different types of testing to the SAP Activate Methodology phases.

Implementation testing takes place during the Realize phase, as partner configuration experts configure processes in the development system's customizing tenant and transport settings to the test and production systems.

Four levels of testing are used:

  • Unit test: Validates a single component of a business process.
  • String test: Validates several connected components in sequence.
  • Authorization test: Confirms users have the correct access to data and functions.
  • End-to-end process test: Validates the complete process.

Unit and string tests are generally informal. Formal testing should be conducted in the test system after integrations are connected and data has been migrated. End-to-end, integration, and data migration tests must be documented in SAP Cloud ALM Test Management.

Note

When a setup instructions document is available in SAP Signavio Process Navigator, complete it before running the test script. It often contains integration or initialization steps required as prerequisites.

User Acceptance Testing

UAT also occurs during the Realize phase. It should be performed by the customer line-of-business experts who participated in Fit-to-Standard workshops because they are well-positioned to confirm the solution meets the original business requirements.

Partner experts create manual test cases in SAP Cloud ALM Test Management; customer experts execute the tests and document results there. All issues must be resolved before the project moves to the Deploy phase.

Regression and Upgrade Testing

Regression testing typically occurs during the Run phase, after go-live. Its purpose is to identify whether a release upgrade affects existing configurations or customizations. Customers are responsible for regression testing post-go-live, though the Test Automation Tool can automate much of this work.

When an upgrade occurs during implementation, the partner team must test all configured processes against the new software version before continuing.

Test automation should be created or updated as each business process is configured. When custom logic modifies a standard process, its automated test must be updated accordingly. After go-live, customers run their own automations for customized processes, while SAP's post-upgrade tests cover standard, unmodified processes.

Note

Use the Scope and Dependencies spreadsheet to plan testing activities. You can find it in SAP Best Practices for SAP S/4HANA Cloud Public Edition→ Accelerators→Getting Started→Availability and dependencies of solution processes.