Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

The BOM transfer function makes it easier for you to assign material components in one or more BOMs to network activities.

Choose the correct answer.
2.

For which of the following dates can you use scheduling?

There are two correct answers.
3.

What business aspects are managed in project planning?

There are three correct answers.
4.

The procurement element for external procurement is a planned order.

Choose the correct answer.
5.

Using the Project Planning Board, you can select WBS elements and schedule the activities assigned to them.

Choose the correct answer.
6.

When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing.

Choose the correct answer.
7.

Which technology is used by the Project Schedule app?

Choose the correct answer.
8.

You can use workforce planning to specify work for internally processed activities.

Choose the correct answer.
9.

The Project Planning Board helps you to create and edit WBS elements and the project definition.

Choose the correct answer.
10.

Which network activity types are used to model externally procured activities?

There are two correct answers.