Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

In what ways can you plan revenues for projects in the SAP Project System (SAP PS)?

There are three correct answers.
2.

When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing.

Choose the correct answer.
3.

The non-stock item category is used for components that are procured via warehouse stock, project stock, or sales order stock.

Choose the correct answer.
4.

What business aspects are managed in project planning?

There are three correct answers.
5.

The procurement element for external procurement is a planned order.

Choose the correct answer.
6.

Which technology is used by the Project Schedule app?

Choose the correct answer.
7.

Which network activity types are used to model externally procured activities?

There are two correct answers.
8.

You can use workforce planning to specify work for internally processed activities.

Choose the correct answer.
9.

The Project Planning Board helps you to create and edit WBS elements and the project definition.

Choose the correct answer.
10.

 Cost planning using activities is the only method used to plan costs for a project in the SAP Project System (PS).

Choose the correct answer.