Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

Using the Project Planning Board, you can select WBS elements and schedule the activities assigned to them.

Choose the correct answer.
2.

The procurement element for external procurement is a planned order.

Choose the correct answer.
3.

 Cost planning using activities is the only method used to plan costs for a project in the SAP Project System (PS).

Choose the correct answer.
4.

In what ways can you plan revenues for projects in the SAP Project System (SAP PS)?

There are three correct answers.
5.

The non-stock item category is used for components that are procured via warehouse stock, project stock, or sales order stock.

Choose the correct answer.
6.

Which technology is used by the Project Schedule app?

Choose the correct answer.
7.

For which of the following dates can you use scheduling?

There are two correct answers.
8.

The BOM transfer function makes it easier for you to assign material components in one or more BOMs to network activities.

Choose the correct answer.
9.

Internally processed activities are used for planning work that is to be carried out outside the company.

Choose the correct answer.
10.

Which network activity types are used to model externally procured activities?

There are two correct answers.