Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

In what ways can you plan revenues for projects in the SAP Project System (SAP PS)?

There are three correct answers.
2.

Which technology is used by the Project Schedule app?

Choose the correct answer.
3.

You can use workforce planning to specify work for internally processed activities.

Choose the correct answer.
4.

The BOM transfer function makes it easier for you to assign material components in one or more BOMs to network activities.

Choose the correct answer.
5.

When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing.

Choose the correct answer.
6.

 Cost planning using activities is the only method used to plan costs for a project in the SAP Project System (PS).

Choose the correct answer.
7.

Using the Project Planning Board, you can select WBS elements and schedule the activities assigned to them.

Choose the correct answer.
8.

The procurement element for external procurement is a planned order.

Choose the correct answer.
9.

What business aspects are managed in project planning?

There are three correct answers.
10.

Which network activity types are used to model externally procured activities?

There are two correct answers.