Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing.

Choose the correct answer.
2.

You can use workforce planning to specify work for internally processed activities.

Choose the correct answer.
3.

 Cost planning using activities is the only method used to plan costs for a project in the SAP Project System (PS).

Choose the correct answer.
4.

Internally processed activities are used for planning work that is to be carried out outside the company.

Choose the correct answer.
5.

For which of the following dates can you use scheduling?

There are two correct answers.
6.

In what ways can you plan revenues for projects in the SAP Project System (SAP PS)?

There are three correct answers.
7.

The BOM transfer function makes it easier for you to assign material components in one or more BOMs to network activities.

Choose the correct answer.
8.

Which technology is used by the Project Schedule app?

Choose the correct answer.
9.

What business aspects are managed in project planning?

There are three correct answers.
10.

Which network activity types are used to model externally procured activities?

There are two correct answers.