Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

The Project Planning Board helps you to create and edit WBS elements and the project definition.

Choose the correct answer.
2.

The procurement element for external procurement is a planned order.

Choose the correct answer.
3.

When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing.

Choose the correct answer.
4.

Internally processed activities are used for planning work that is to be carried out outside the company.

Choose the correct answer.
5.

In what ways can you plan revenues for projects in the SAP Project System (SAP PS)?

There are three correct answers.
6.

The BOM transfer function makes it easier for you to assign material components in one or more BOMs to network activities.

Choose the correct answer.
7.

What business aspects are managed in project planning?

There are three correct answers.
8.

The non-stock item category is used for components that are procured via warehouse stock, project stock, or sales order stock.

Choose the correct answer.
9.

You can use workforce planning to specify work for internally processed activities.

Choose the correct answer.
10.

 Cost planning using activities is the only method used to plan costs for a project in the SAP Project System (PS).

Choose the correct answer.