Initiating the Project in the Prepare Phase

Getting Started with your Implementation

Objective

After completing this lesson, you will be able to describe the key activities of the Prepare phase, including initiating the project, completing customer onboarding through embedded launch activities and orientation training, and establishing project governance, documentation, and management frameworks.

The Prepare Phase

The purpose of the Prepare phase is to provide the initial planning and preparation for the project.

High level diagram of 6 phases of SAP Activate methodology with the Prepare phase highlighted.

In this phase, the project is started, plans are discussed in more detail and finalized, the project team is assigned, and work is underway to start the project optimally.

Key Prepare Activities

  • Define project goals, a high-level scope, and a project plan

  • Identify and quantify business value objectives

  • Establish project standards, organization, and governance

  • Define and secure approval for the implementation/upgrade strategy

  • Define roles and responsibilities for the project team

  • Validate the project objectives

  • Establish project management, tracking, and reporting mechanisms for value delivery

  • Develop a project team training strategy, and start project team training

  • Document all initiation activities in the project charter. Generally, the Statement of Work (SOW) acts as the Project Charter.

  • Pre-assemble (or establish) the project environment, infrastructure, and IT systems including SAP Solution Manager

  • Prepare for the Explore phase

Start the Project

Now that you understand the strategic importance of the Prepare phase, it’s time to look at the first practical steps a customer takes to officially start their project.

SAP provides a structured set of resources to guide you through this initial stage, ensuring your team is set up for success from day one. This brings us to the initial key activities such as joining embedded launch activities and attending Project Team Orientation Training.

Join Embedded SuccessLaunch Activities (EmLA) in SAP SuccessFactors Onboarding Journey

In preparation for implementing SAP SuccessFactors, onboarding services are included with the customer’s SAP SuccessFactors subscription, including embedded launch activities. They offer a structured onboarding experience centered on leading practices and guided enablement to ensure a smooth implementation, supporting your team's success in deploying and adopting SAP solutions.

  1. Register and join live monthly SAP SuccessFactors Onboarding Webcasts to connect with Onboarding Experts who will walk you through key onboarding topics, such as initial access, provisioning and key onboarding resources available to help you ensure a rapid and success deployment.

  2. Visit and bookmark our SAP SuccessFactors Onboarding Resource Center, your one-stop shop for all onboarding resources, available as a self-service onboarding companion.

  3. Follow the guidance listed in the Embedded Launch Activities Customer Guide. This includes:

    • Invest in Guided Enablement to learn about global leading practices.
    • Experience leading practices through access to a pre-configured Demo Environment.
    • Request a Deployment Readiness Check to help safeguard deployment.

You can reach out to your Customer Onboarding Team for any questions via the email SAP_SuccessFactors_Onboarding@sap.com.

Attend Project Team Orientation Training

Project Team Orientation Training is an asynchronous pre-built standard online training available for Customer resources to prepare themselves for the implementation of each module. The training is very high level but introduces the Customer to SAP and SuccessFactors terms, activities, and notions to align them on their implementation journey.

SAP Implementor Activities During the Prepare Phase

Introduction

While the customer is joining EmLA sessions and completing orientation training, the SAP Implementor is simultaneously laying the operational groundwork for the project. These activities establish the structure, cadence, and artifacts that will govern the engagement from the Prepare phase through to the Run phase.

Build Project Documentation from Templates

To ensure consistency and professional standards, start by building your core project documentation using approved templates:

  • Project charter
  • Communication plan
  • Resource and staffing plan
  • Roles and responsibilities (RACI)
  • Kickoff deck

Build and Socialize the Project Schedule

A well-defined schedule is the backbone of project management. Follow these steps to establish your timeline:

  • Draft the integrated project schedule aligned to SAP Activate phases.
  • Identify key milestones, dependencies, and the critical path.
  • Socialize the schedule with customer stakeholders and secure their sign-off.
  • Publish the baseline schedule to track progress.

Establish the PTO and Availability Calendar

Managing availability is crucial for maintaining project momentum. You should:

  • Capture planned time off for both the Implementor and customer teams.
  • Overlay these dates against the schedule to flag potential capacity risks.
  • Maintain this calendar as a living document throughout the project.

Start the Risks, Assumptions, Issues, and Dependencies (RAID) Log

The RAID log helps you proactively manage project health by tracking specific variables:

  • Define the initial Risks, Assumptions, Issues, and Dependencies.
  • Establish a clear intake, triage, and escalation process.
  • Assign an owner and set a regular review cadence.

Set Up Recurring Meetings and Governance Cadence

Establish a rhythm for communication and decision-making through the following meetings:

  • Weekly project team status updates.
  • Workstream or module-specific working sessions.
  • Executive Steering Committee (Steer Co) meetings to discuss cadence, attendees, and decision rights.
  • Change control board meetings, if applicable to your project scope.

Build the First Status Report

The first status report sets the standard for all future reporting. Ensure you:

  • Establish the reporting template, including RAG (Red, Amber, Green) status, milestones, RAID summary, and next steps.
  • Confirm the distribution list and the cadence for delivery.
  • Publish the first report to set the project baseline.

Set Up Collaboration Tooling and Project Environment

Finally, ensure the team has the right environment to work together effectively:

  • Set up collaboration sites such as SharePoint or Teams, shared drives, and ticketing or issue trackers.
  • Manage access provisioning for both the Implementor and customer teams.

Case Study: What Pinnacle Industries Did During the Prepare Phase

With SAP SuccessFactors selected as their HCM solution, Pinnacle Industries moved into the Prepare Phase and focused on establishing the right foundations before any configuration work could begin.

Key Activities During the Prepare Phase

  • Customer:
    • Joined the SAP SuccessFactors Embedded Launch Activities (EmLA) to onboard their project team and align on implementation leading practices
    • Attended Project Team Orientation Training to familiarize the client team with SAP SuccessFactors terminology, processes, and implementation concepts
  • SAP Implementor
    • Delivered a baseline project schedule and socialized it with Pinnacle leadership
    • Established a weekly status cadence and bi-weekly Steer Co meeting
    • Launched the RAID log and PTO calendar; distributed the first weekly status report
    • Provisioned the shared project workspace and document repository

Outcome

Ensured the project team was trained and aligned to begin implementation work

Summary

  • Purpose of the Prepare Phase: Focuses on initial planning, establishing project governance, and assigning the project team to ensure a structured start to the implementation.
  • Core Activities: Includes defining project goals, securing executive sponsorship, developing a training strategy, and setting up the technical environment, including SAP Solution Manager.
  • SAP SuccessFactors Onboarding: Features Embedded Launch Activities (EmLA) for leading practice adoption and a Deployment Readiness Check to safeguard project progress.
  • Project Team Orientation Training: Provides asynchronous online training to align the customer team on SAP SuccessFactors terminology, processes, and implementation concepts.