Organizing supply timing variability

Objective

After completing this lesson, you will be able to organize supply timing variability.

Supply Variability Factors

From a standard order, you deal with lead time uncertainty. This can mean timing for late deliveries.

The figure describes the Lead Time Uncertainty.

Lead Time Variability

Safety stock is often required to hedge against uncertainty in delivery and manufacturing lead times. Lead time variability (standard deviation around the mean):

  • Captures variations in lead times due to natural, external forces

  • Does not include the effects of expediting and advance order placements (we do not plan to expedite)

  • Does not include the effects of upstream material unavailability (that is a different measurement)

Note

The algorithm for handling lead time variability is based on internal research and is proprietary to SAP. Lead time variability is an input to the SAP IBP for inventory application.
The figure describes the Lead Time Variability.

Lead Time (LT) Standard Deviation

Inserting a number in the LT Standard Deviation field means that SAP takes into account LT variability in the calculation of safety stock. SAP then assumes a shipment may arrive late, about 50% of the time. The LT StdDev shows the system how late the shipment may arrive and the probability of lateness. The higher the LT StdDev value, the later the shipment arrives.

This potential late shipment is then combined with other uncertainties in the supply chain and this figure is used to calculate safety stock. LT uncertainty also adds to potential exposure in the supply chain.

This field accepts non-zero values and they do not need to be integers.

The figure describes the LT Standard Deviation.

Incorporating Variability and Uncertainty

Forecast error variability captures errors around forecasts.

Service variability captures intentional, less-than-perfect service from internal replenishment points, due to multi-stage optimization.

Lead time variability captures variations in lead times due to natural external forces. Lead time does not include the effects of expediting and advance order placements. Lead time does not include the effects of upstream material unavailability.

The figure describes the Variability and Uncertainty.

What is Lead Time?

Total lead time is the time between when an order is placed and when it is received.

The figure describes the Lead Time.

What is Lead Time Variability?

Actual lead time varies from mean lead time due to delays or faster processing.

The figure describes the actual Lead Time.

Why is Lead Time Variability Important?

Lead time variability creates the risk that order receipts may be delayed.

Order delays can result in a shortfall in inventory position.

Ignoring lead time variability negatively impacts service level.

The figure describes the Lead Time.

What are the Basic Lead Time Approaches?

The basic approaches are as follows:

  • Plan for average lead time.
  • Plan for maximum lead time (the worst case scenario).

The typical trends and tendencies for both approaches can be derived from the table shown in the following figure.

The figure describes the Basic Approaches.

What is the Correct Approach to Planning?

In contrast to SAP IBP for inventory, pure academic formulas simply ignore many of the important complexities in planning.

The figure describes the complex approach.

Examples of Real World Complexities Ignored by Simple Approaches

Based on the following figure, let’s look at an example:

  • Does lead time variability at IN affect inventory shortfall at CF?
  • Is this impact affected by the inventory decision (SS) at IN?

Example: Is CF shortfall the same if SS(IN) = 0 vs. SS(IN) = 1000?

Is the shortfall at IN and/or CF the same in every period if demand is time varying?

The figure shows an example for complexities.

Comparing the Different Approaches

Let’s look at the following figure and compare the three different approaches:

  • Plan for average lead time
  • Plan for worst case lead time
  • The SAP IBP for inventory approach
The figure describes the comparison approach.

What is Order Crossover?

Case 1

Two consecutive orders arrive. Each has an LT = 2. The orders are covered by receipts using the First Come, First Served (FCFS) principle.

The figure describes the Order Crossover Case 1.

Case 2

The first order is delayed, but the second order arrives earlier.

The lead time of the first order = 3 and the lead time of the second order = 1.

Orders are not received in the same sequence and this is termed order crossover.

There are multiple scenarios for the values of the actual lead time of the two orders.

Think about which have order crossovers and which do not.

The figure describes the Order Crossover Case 2.

When Can Order Crossovers Occur?

Principally, order crossovers can occur:

  • When orders are not processed, based on a First Come, First Served (FCFS) policy.
  • When there are multiple transportation modes or providers.
  • When orders are processed in parallel.
  • When there are multiple suppliers.
  • When there is variability in transportation time due to factors like geography and weather.

What is the Impact of Order Crossovers?

Ignoring order crossover causes significant overestimation of inventory shortfall and hence safety stock requirements.

The figure describes the Order Crossover Impact.

This can also be seen from the total statistics in the order crossover table.

The figure describes the Order Crossover Table.

What is the Impact of PBR?

Let’s simulate the impact of a rising PBR for a crossover scenario, first we assume PBR = 1.

The figure describes the Impact of PBR.

Next, the PBR increases to 2, all other parameters remain unchanged.

The figure describes the Impact of PBR.

With the PBR being increased to 3, the tendency becomes clear for our example. The higher the interval between orders, the lower the chance for order crossovers.

The figure describes the Impact of PBR.

What is the Impact of Batch Size?

As the figure shows, large batch sizes increase the interval between orders. This reduces the chance for order crossovers as before.

The figure describes the Impact of Batch Size.

What is the Impact on Inventory Requirements?

With regard to the batch size, we make the following observations:

  • The average on-hand inventory increases with batch size in both scenarios.
  • The on-hand inventory can be lower when the impact of order crossover is considered.
The figure describes the Batch Size.

For our example, these tendencies can be derived in numbers from the table in the following figure.

The figure describes the Batch Size Table.

What is the Impact of Increasing Lead Time Variability?

Safety stock always increases with lead time variability, as shown in the following figure.

When lead time standard deviation is very small relative to lead time:

  • Order crossover does not occur
  • Safety stock decreases as batch size increases

When lead time variability is high:

  • Order crossover occurs when batch size is relatively small.
  • Safety stock increases asymptotically as batch size increases. For example, it reaches a limit.
The figure describes the Lead Time Variability.