Assigning Reference Points to the Major Assembly BOM Items (Installation Kits)

Objective

After completing this lesson, you will be able to assign reference points to BOM items and corresponding network activities for accuracy in BOM transfer process.

Reference Points

A major assembly uses networks and BOMs to assign components to network activities for installation kits tailored to engineering or customer requirements.

Reference points define where in the activity network an installation kit will be assembled. Network activities have reference points and manufacturing BOM items also have reference points. If the reference point of the manufacturing BOM item and the reference point of the network activity match, then the manufacturing BOM item is assigned to the network activity. Reference points are a prerequisite of the manufacturing BOM maintenance.

Hint

Major assemblies can have several hundred installation kits and every installation kit needs a unique reference point. Therefore, you should create the reference points in a systematic way.

In Customizing for Project System→Bill of Material Transfer→Define Reference Points for BOM Transfer, you define reference points which you can then use as a logical link between BOM items (installation kits) and network activities.

screenshots of Reference Points for BOM Transfer

Note

You have to define a reference point in this Customizing activity before you can use it in the reference point field in the BOM item or network activity.

You should assign reference points to network activities in the project. If you use a template to create a new project, the reference points will be maintained in the network activities of the template and will be copied with them to a new project. You can modify them as required in the Assignments tab of the network activity.

Screenshot of assignments tab

The same reference points shall be assigned to BOM items (installation kits) of the major assembly. Every time the BOM-PS Interface is executed, the system compares the reference points of all the selected BOM components and all the selected network activities. If there is a match, the system creates, changes, or deletes the BOM components in the corresponding network activities.

Chart showing Major Assembly From BOM to WBS Element

Summary

This lesson covers assigning reference points to BOM items and network activities for precise BOM transfer.

  • Use reference points to link BOM items with network activities for tailored assembly.
  • Define reference points systematically to manage numerous installation kits efficiently.
  • Assign reference points in Customizing to enable accurate BOM and activity matching.
  • Utilize project templates to streamline reference point assignment.
  • Ensure smooth BOM-PS Interface execution by aligning component and activity reference points.

Assign Reference Points to the Major Assembly

Business Example

John is a production engineer with the low-volume A&D company focusing on the final assembly of complex products. He has already created an MBOM for a major assembly and now has to assign reference points to its BOM items (installation kits) to do BOM explosion for the major assembly and assign installation kits to the project’s network activities.