The complex assembly process starts with the creation of a project for a new model and unit of an end item. The project coordinates the subsequent process steps such as product engineering, production engineering, production planning, and production execution. The process aims at fulfilling the following objectives:
- Tight integration of engineering and production execution
- Support individually configured end items by means of parameter effectivity
- Top-down project planning
- Support the collaboration of people with different roles
- Check and validate user entry to prevent errors early and make the process more robust
- Automate process steps that can be automated. In the figure, Complex Assembly Process, the clock indicates a periodic job
- Record all process steps for later reference, root-cause analysis, and process improvement activities
The following figure shows an overview of the complex assembly process. This unit explains the details of the process.


Design Engineer: The process starts with design engineering where product engineers develop engineering BOMs (EBOMs) for the end item and major assemblies. They tailor BOM items based on customer preferences and restrict their validity accordingly.
Production Engineer: Once the EBOMs are created and released, production engineering takes over. Production engineers design the assembly process, organizing major assembly components into installation kits and creating routings for each. By releasing MBOMs and routings, they signal production planners that the design phase is complete.
Production Planner: In production planning, the production planner initiates a project for the end item, scheduling start and end dates for each installation kit by organizing network activities. MRP uses these schedules to set requirement dates, automatically generating planned orders, which convert to production orders when ready.
Production Supervisor: Although major assemblies are not directly seen in production planning, they are reflected in project networks, allowing supervisors to manage and oversee the assembly processes as depicted by project system networks.
Production Operator: Production operators follow scheduling and sequence control dictated by these network activities to ensure smooth production flow.
Installation kits are represented both in the project system and PEO, captured as activities within a major assembly’s network.

The production orders are managed and executed in production operations. Production supervisors release the production orders as soon as all prerequisites for starting production have been fulfilled. This communicates to the production operators that they can start work on the production order. The production operators then assemble installation kit components into the major assembly as instructed by the installation order (production order for the installation kit). On completion of the installation order, an artificial inventory for the installation kit is posted. This inventory is cleared automatically by a periodic job.