Demonstrating the CM to CM Scenario

Objective

After completing this lesson, you will be able to Demonstrate the CM to CM Scenario.

Create the Stock Transport Order

The first step is to create the Stock Transport Order. This is similar to creating a Purchase Order. We use ME21N but specify the order type as Stock Transp. Order. The fields we populate at the header include the Supplying Plant, Purchase Organization, Purchasing Group, and Company Code.

At the line level, we provide the Material, Quantity, Plant (which is the Receiving Plant), and the Issuing Storage Location. Both the Supplying and Receiving Plants are virtual plants. At the Item Detail level, we provide the appropriate confirmation control key value.

Screenshot of creating the STO in SAP.

Add the Business Partner

On the Partners tab, add the Business Partner for the Receiving Plant.

Screenshot of specifying the Partner on the header of the STO.

Create the Stock Transport Order

Test your knowledge by using the following simulation to create the Stock Transport Order.

Create the Advance Ship Notice, Check the Outbound Delivery, Goods Issue, and Inbound Delivery

The Supplying Plant creates the Advance Ship Notice on the SAP Business Network.

Screenshot of creating the Advance Ship Notice.

The Outbound Delivery and the Goods Issue are Displayed

After the Advance Ship Notice has been created on the SAP Business Network, we see the Outbound Delivery (Tr./Ev. Delivery note) and the Goods Issue (Tr./Ev. Goods Issue) on the SAP System.

Screenshot of the Outbound Delivery and the Goods Issue on the SAP System.

The Inbound Delivery is Displayed

On the Confirmation tab of the Stock Transport Order we see a reference to the Inbound Delivery (180005779).

Screenshot of the Inbound Delivery on the Stock Transport Order.

Create the Advance Ship Notice and Check the Outbound and Inbound Delivery

Test your knowledge by using the following simulation to create the Advance Ship Notice and check the Outbound Delivery, the Goods Issue, and the Inbound Delivery.

Create the Component Receipt

Display the Advance Ship Notice

The Receiving Plant is able to see the Advance Ship Notice created by the Supplying Plant. They will use this to create the Component Receipt.

Screenshot showing the Advance Ship Notice copy is received by the Receiving Plant.

Create the Component Receipt

The Receiving Plant has received the stock so they will create a Component Receipt.

Screenshot of creating the Component Receipt by the Receiving Plant.

The Component Receipt sent by the Receiving Plant is received by the OEM in the SAP System as a Goods Receipt.

Screenshot of the Goods Receipt received by the OEM in the SAP System.

The Supplying Plant Receives the Goods Receipt

The Goods Receipt in SAP is forwarded to the Business Partner representing the Supplying Plant and received in the SAP Business Network.

Screenshot of creating the Component Receipt by the Receiving Plant.

Create the Component Receipt

Create the Component Receipt

Test your knowledge by using the following simulation to create the Component Receipt

Log in to track your progress & complete quizzes