Setting Up Material Master Records

Objective

After completing this lesson, you will be able to define basic settings for material master records

Overview of Settings for Material Master Records

Functions Performed in Customizing

Perform the following functions in Customizing, under the Tools node:

  • Define authorizations and authorization profiles for the maintenance of material master records
  • Organize the data transfer for material master records
  • Specify the start times of background jobs
  • Maintain search help
  • Reset test data
  • Initialize the periods for the individual company codes

Basic Settings for Material Master Records

The basic settings for the material type are as follows:

  • Output format of material numbers
  • Global settings
  • Company codes for materials management
  • Material types and number ranges
  • Properties of system messages during material master maintenance

Specify the following data in Customizing, under the Global Settings node:

  • The type of administrative data update for the technical data (table MSTA) during the processing of material master records:

    The system updates the material administration data whenever you create or change material master records. You can use the (Information on material) option in a material master record to see relevant information.

    You can choose one of the following settings:
    • The update is to take place only at the table level (such as at client level, plant level, and so on).
    • The update has to depend on each maintenance status (such as MRP, Purchasing, and so on) and data-retention level (such as client, plant, and so on).
    • Data must not be updated.
  • Document type:

    The standard document type for engineering or design drawings, if your company uses the document management system.

Activate certain special applications of reference materials, such as, using follow-up materials or manufacturer part numbers, by selecting a checkbox.

Maintenance of Company Codes for Materials

Company Code Initialization

SAP interface for initializing periods in Material Master Records, allowing users to input company codes, fiscal years, and specific dates to set the next period for record updates and management.

For the monthly closing of an accounting period in materials management, you use the period closing program. To call this program, on the SAP Easy Access screen, choose LogisticsMaterials ManagementMaterial MasterOtherClose Period (MMPV).

Note

You cannot reverse the closing of a period by using the period closing program. If you accidentally close the period, you must re-initialize it (see SAP Note 487381).