It's time to put what you've learned to the test, get 8 right to pass this unit.
1.
The lot size specified in the quota arrangement item overrides the settings in the material master record for the planning run. True or false?
Choose the correct answer.
2.
During the requirements planning run, according to what priority does the system determine the possible sources?
Choose the correct answer.
3.
You can enter only suppliers and plants in the quota arrangement, but no outline agreement items. True or false?
Choose the correct answer.
4.
In automatic source determination, the system can find sources for an item without a material master record even if the material group of the outline agreement item or info record is different from the material group of the requested material. True or false?
Choose the correct answer.
5.
How do you block sources of supply?
There are two correct answers.
6.
For transactions outside the planning run, what flow logic does the system use for source determination?
Choose the correct answer.
7.
You can use the source list to prevent materials from being ordered with reference to a material group contract item. True or false?
Choose the correct answer.
8.
The total quantity of all relevant assigned planned orders for a material goes into the quota-allocated quantity. If the planned order is converted to a requisition, the quota-allocated quantity is updated once more. True or false?
Choose the correct answer.
9.
If the Source list indicator has been set in the material master record, it is not possible to create a purchase requisition or purchase order for a supplier that is not in the source list. True or false?
Choose the correct answer.
10.
Which of the following is the calculation for quota rating?