Knowledge quiz

It's time to put what you've learned to the test, get 8 right to pass this unit.

1.

If you copy a reference operation set from a routing, only the basic sequence is copied.

Choose the correct answer.
2.

The in-house production time for a __________ can be calculated using lead-time scheduling.

Choose the correct answer.
3.

If material requirements planning (MRP) is carried out without lead-time scheduling, it calculates capacity requirements.

Choose the correct answer.
4.

In the simplest case, a routing has one sequence, the __________ sequence.

Choose the correct answer.
5.

You can create parallel sequences in which of the following task lists?

There are two correct answers.
6.

Which of the following are possible reasons for alternative production methods?

Choose the correct answer.
7.

You can use a scheduling margin key to define the floats before and after production in the material master record.

Choose the correct answer.
8.

Which of the following is the main reason for an alternative production method being required for different production lots?

Choose the correct answer.
9.

When you display change master changes inside your routing, what kind of display options are available?

Choose the correct answer.
10.

Which of the following can you assign to an operation in a reference operation set?

Choose the correct answer.