Based on planned, actual, and commitment values, the system determines the remaining costs in network activities. The system includes the following:
All actual and commitment values in the project.
The plan values for the network activities in Controlling version 0.
Forecast values from confirmations.
The system ignores the following:
Based on planned, actual, and commitment costs, the system determines what needs to be done in network activities and costs. The system records the value determined as cost to complete, by period, in a cost forecast version for internally processed activities, externally processed activities, general cost activities, and material components that are not maintained as part of project stock (valuated or non-valuated).
Values are usually determined from the first day of the current period, as part of the period-end closing process. You have the option to specify your own key date for the cost forecast. The system uses the key date to determine the cost distribution.
You determine residual costs similar to the way in which you calculate planned values. The basis for residual costs calculation is the planned costing variant defined in the network header for calculating planned costs.
If an activity is marked as complete or there is a final confirmation, the system sets the cost to complete to zero.